Which of the ten knowledge areas defined in the Project Management Body of Knowledge includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully? a. Project scope management b. Project quality management c. Project communications management d. Project stakeholder management - Answer -a. Project scope management Which of the ten knowledge areas defined in the Project Management Body of Knowledge includes the activities of purchasing or acquiring products, services or results from outside the project team? a. Scope management b. Quality management c. Communications management d. Procurement management - Answer -d. Procurement management Achieving project success is determined by all of the following EXCEPT :a. creating deliverables that include all required features b. involving only important key stakeholders c. completing the project on schedule and on budget d. providing outputs that please the project's customers - Answer -b. involving only important key stakeholders Projects are considered successful for all of the reasons below EXCEPT: .a. members of the team learn new skills working on the project. b. the organization captures lessons learned for future projects. c. the team has demonstrated heroics to meet project objectives d. the organization reaps business level benefits. - Answer -c. the team has demonstrated heroics to meet project objectives Which of the following actions will likely cause a project to fail? a. dedicating valuable team member time to identify risk events b. spending project funding to procure needed tools and spare parts c. unclear or conflicting stakeholder expectations d. conducting a project audit to evaluate performance - Answer -c. unclear or conflicting stakeholder expectations Project failure can result from all of the following causes EXCEPT: a. support of senior management b. changes in scope are not agreed upon by all parties involved. c. too little time is allowed for project completion. d. planning is not adequate. - Answer -a. support of senior management A project manager in agile projects who serves and leads in a collaborative, facilitation manner is called a:

Content preview

SCMA 350 FINAL QUESTIONS & ANSWERS

Which of the following examples is NOT a typical or appropriate situation to employ
project management?

a. improving an existing work process
b. installing a new computer system
c. conducting a routine, standard customer service operation
d. developing a new product - Answer -c. conducting a routine, standard customer
service operation

Which of the following examples is NOT a typical or appropriate situation to employ
project management?

a. improving a soldering process in an assembly line
b. processing deposits and withdrawals in a bank
c. installing a new accounting application on to a server
d. developing a new medical device for use by clinics - Answer -b. processing deposits
and withdrawals in a bank

In the PMBOK, the five logical groupings of the project management inputs, tools and
techniques, and outputs are called the:

a. project management knowledge areas
b. project management process groups
c. life cycle stages
d. phases and gates - Answer -b. project management process groups

When applied to project management, the human resource management knowledge
area typically involves which of the following activities?

a. determining the work necessary for project completion
b. estimating, budgeting and controlling project costs
c. identifying, analyzing and controlling project risks
d. organizing, managing and leading the project team - Answer -d. organizing,
managing and leading the project team

Which of the ten knowledge areas defined in the Project Management Body of
Knowledge includes the processes required to ensure that the project includes all the
work required, and only the work required, to complete the project successfully?

a. Project scope management
b. Project quality management
c. Project communications management
d. Project stakeholder management - Answer -a. Project scope management

,Which of the ten knowledge areas defined in the Project Management Body of
Knowledge includes the activities of purchasing or acquiring products, services or
results from outside the project team?

a. Scope management
b. Quality management
c. Communications management
d. Procurement management - Answer -d. Procurement management

Achieving project success is determined by all of the following EXCEPT

:a. creating deliverables that include all required features
b. involving only important key stakeholders
c. completing the project on schedule and on budget
d. providing outputs that please the project's customers - Answer -b. involving only
important key stakeholders

Projects are considered successful for all of the reasons below EXCEPT:

.a. members of the team learn new skills working on the project.
b. the organization captures lessons learned for future projects.
c. the team has demonstrated heroics to meet project objectives
d. the organization reaps business level benefits. - Answer -c. the team has
demonstrated heroics to meet project objectives

Which of the following actions will likely cause a project to fail?

a. dedicating valuable team member time to identify risk events
b. spending project funding to procure needed tools and spare parts
c. unclear or conflicting stakeholder expectations
d. conducting a project audit to evaluate performance - Answer -c. unclear or conflicting
stakeholder expectations

Project failure can result from all of the following causes EXCEPT:

a. support of senior management
b. changes in scope are not agreed upon by all parties involved.
c. too little time is allowed for project completion.
d. planning is not adequate. - Answer -a. support of senior management

A project manager in agile projects who serves and leads in a collaborative, facilitation
manner is called a:

a. program manager
b. scrum master

,c. sponsor
d. functional manager - Answer -b. scrum master

Typically, a steering team or leadership team is responsible for all of the following
project related roles EXCEPT:

a. selecting, prioritizing and resourcing projects
b. providing rigid policies, procedures, standards and guidelines
c. ensuring accurate progress is reported and adjustments made
d. aligning projects with the organization's strategic plans - Answer -b. providing rigid
policies, procedures, standards and guidelines

All of the following factors have influenced the increased reliance upon project
management in recent years EXCEPT:

a. rapid growth and changes in the information technology and telecommunications
industries
b. realization that methods for large projects can be modified and used for small
projects
c. increased international competition and its influence on consumer demands
d. the decreased demands of ongoing operational work - Answer -d. the decreased
demands of ongoing operational work

Projects often require tradeoffs among all of the following EXCEPT:

a. scope
b. cost
c. schedule
d. programs - Answer -d. programs

Once projects are completed, they will typically yield all of the following results
EXCEPT:
a. a unique product, service or result
b. make or buy decisions
c. stakeholders whose interests are affected by the outcome
d. a primary deliverable along with supporting deliverables - Answer -b. make or buy
decisions

In an adaptive or change - driven project life cycle:

a. the product or deliverable is well understood.
b. planning precedes all executing.
c. early results lead into planning later work.
d. the waterfall approach is commonly used. - Answer -c. early results lead into
planning later work.

, Which of the following statements correctly describes project management?

a. Project management applies knowledge, skills, tools and techniques to project
activities.
b. Project management should not involve tradeoffs between scope, schedule and cost.
c. Project management only relies upon checklists to plan and execute the work.
d. Project management's goal is to maintain efficiency of ongoing operations. - Answer
-a. Project management applies knowledge, skills, tools and techniques to project
activities.

Which of the following statements regarding project life cycles is most accurate?

a. All research and development organizations rely upon a four-stage project life cycle
that includes initiating, planning, executing and closing.
b. The project life cycle is the same regardless of the type of projects managed by an
organization.
c. Many different project life cycle models are used, for different types of projects.
d. All project life cycles are the same across every industry - Answer -c. Many different
project life cycle models are used, for different types of projects.

Which of the following roles is typically associated with the project manager?

a. the person assigned by the performing organization to lead the team that is
responsible for achieving the project objectives
b. the person with management authority over a unit within a functional organization
c. the person responsible for project methods, standards and training
d. the person responsible for providing the financial resources and support for the
project and is accountable for enabling success. - Answer -a. the person assigned by
the performing organization to lead the team that is responsible for achieving the project
objectives

Typically, the senior customer representative is responsible for which of the following
project roles?

a. develops the project schedule and budget
b. determines how the project work will be accomplished
c. ensures the needs of the customer's organization are identified and prioritized
d. helps the project manager with running meetings and providing status reports -
Answer -c. ensures the needs of the customer's organization are identified and
prioritized

From an agile project management perspective, which of these constraints are
considered to be fixed?

a. Quality and value
b. Resources and schedule

Document information

Uploaded on
August 4, 2025
Number of pages
65
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$18.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA
3.8
(361)
Sold
2134
Followers
1447
Items
58437
Last sold
5 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions