Professional Scrum Master I (PSM I) Exam
Questions and Verified Answers 2025
How much work must a Development Team do to a Product Backlog item it selects
for a Sprint? -Correct Answer ✔As much as it has told the Product Owner will be
done for every Product Backlog item it selects in conformance with the definition
of "Done".
*Reason:* The purpose of each Sprint is to deliver Increments of potentially
releasable functionality that adhere to the Scrum Team's current definition of
"Done".
*True or False:* The Scrum Team should choose at least one high priority process
improvement, identified during the Sprint Retrospective, and place it in the Product
Backlog. -Correct Answer ✔False
*Reason:* To ensure continuous improvement, the Sprint Backlog rather than the
Product Backlog includes at least one high priority process improvement identified
in the previous Sprint Retrospective meeting.
*True or False:* When multiple teams work together on the same product, each
team should maintain a separate Product Backlog. -Correct Answer ✔False
*Reason:* Products have one Product Backlog, regardless of how many teams are
used. Any other setup makes it difficult for the Development Team to determine
what it should work on.
PSM
, PSM
Who is responsible for managing the progress of work during a Sprint? -Correct
Answer ✔The Development Team
*Reason:* The Development Team uses the Daily Scrum to inspect progress
toward the Sprint Goal and to inspect how progress is trending toward completing
the work in the Sprint Backlog.
*True or False:* It is mandatory that the product increment be released to
production at the end of each Sprint. -Correct Answer ✔False
*Reason:* The product increment should be usable and releasable at the end of
every Sprint, but it does not have to be released.
The Development Team should have all the skills needed to: -Correct Answer
✔Turn the Product Backlog items it selects into an increment of potentially
releasable product functionality.
*Reason:* The Development Team consists of professionals who do the work of
delivering a potentially releasable Increment of "Done" product at the end of each
Sprint. Development Teams are cross-functional, with all of the skills as a team
necessary to create a product Increment.
Which of the below are roles on a Scrum Team?
Alternatively: Who is on the Scrum Team? -Correct Answer ✔Development Team,
Product Owner, Scrum Master