IDPX Mid-Point Exam Questions And
Answers
Which of these would an interior designer put into a schedule?
hardware
finish
door/ window
all of the above -
correct answer ✅all of the above
On an electrical plan, what does the following symbol represent?
duplex outlet
double switch
dimmer switch
3-way switch -
correct answer ✅dimmer switch
On what sheet of a construction drawing set would be the most
logical location for the door schedule?
On the partition plan
On the title sheet with the general notes
,IDPX Mid-Point Exam Questions And
Answers
On the details sheet
None of these -
correct answer ✅On the partition plan
What mark is placed on a floor plan to indicate that an elevation of
a wall or walls is drawn somewhere in the drawing set?
an elevation reference
reference bubble
a detail reference
a section reference -
correct answer ✅an elevation reference
Which symbol represents a quadruplex outlet?
A
B
C
D-
correct answer ✅C
,IDPX Mid-Point Exam Questions And
Answers
A quadruplex receptacle is represented by 2 perpendicular lines
crossing through a standard duplex symbol.
The top number inside each symbol refers to what in a set of
working construction documents? -
correct answer ✅Indicates the sequential drawing number
Which of the following drawings would be most needed to begin
space planning in an existing building?
circulation plan
egress plan
reflected ceiling plan
base plan -
correct answer ✅base plan
What does this symbol represent?
Telephone
Data
Power and data
Data and telephone -
correct answer ✅Data and telephone
, IDPX Mid-Point Exam Questions And
Answers
What does this symbol represent? -
correct answer ✅Telephone jack
What symbol is represented by an open triangle? -
correct answer ✅Data jack
Which type of drawing is used to show items that are up to 48" (1.2
m) AFF?
floor plan
axonometric
orthographic projection
elevation -
correct answer ✅floor plan
Which millwork finish would be the best choice to use for the front
desk that takes a lot of abuse in a very busy hotel lobby?
polyurethane
stain
polyester
Answers
Which of these would an interior designer put into a schedule?
hardware
finish
door/ window
all of the above -
correct answer ✅all of the above
On an electrical plan, what does the following symbol represent?
duplex outlet
double switch
dimmer switch
3-way switch -
correct answer ✅dimmer switch
On what sheet of a construction drawing set would be the most
logical location for the door schedule?
On the partition plan
On the title sheet with the general notes
,IDPX Mid-Point Exam Questions And
Answers
On the details sheet
None of these -
correct answer ✅On the partition plan
What mark is placed on a floor plan to indicate that an elevation of
a wall or walls is drawn somewhere in the drawing set?
an elevation reference
reference bubble
a detail reference
a section reference -
correct answer ✅an elevation reference
Which symbol represents a quadruplex outlet?
A
B
C
D-
correct answer ✅C
,IDPX Mid-Point Exam Questions And
Answers
A quadruplex receptacle is represented by 2 perpendicular lines
crossing through a standard duplex symbol.
The top number inside each symbol refers to what in a set of
working construction documents? -
correct answer ✅Indicates the sequential drawing number
Which of the following drawings would be most needed to begin
space planning in an existing building?
circulation plan
egress plan
reflected ceiling plan
base plan -
correct answer ✅base plan
What does this symbol represent?
Telephone
Data
Power and data
Data and telephone -
correct answer ✅Data and telephone
, IDPX Mid-Point Exam Questions And
Answers
What does this symbol represent? -
correct answer ✅Telephone jack
What symbol is represented by an open triangle? -
correct answer ✅Data jack
Which type of drawing is used to show items that are up to 48" (1.2
m) AFF?
floor plan
axonometric
orthographic projection
elevation -
correct answer ✅floor plan
Which millwork finish would be the best choice to use for the front
desk that takes a lot of abuse in a very busy hotel lobby?
polyurethane
stain
polyester