.ANSWER-The .Clean .Water .Act
Regulations .for .managing .stormwater .activity .on .a .construction .site .are
.outlined .in .the .- .CORRECT .ANSWER-NPDES
When .should .you .read .and .understand .your .project .stormwater .pollution
.prevention .plan .- .CORRECT .ANSWER-Immediately .after .the .project .awarded
.and .before .you .begin .any .site .work .is
Which .of .the .following .is .not .an .allowable .stormwater .discharge .or .non-
stormwater .discharge .- .CORRECT .ANSWER-Discharges .are .contaminated
.groundwater
Construction .activity .may .begin .- .CORRECT .ANSWER-When .the .jurisdiction .of
.operation .specifies .you .can .start
Waters .that .sell .anti-degration .standards .are .placed .on .the . .list .-
.CORRECT .ANSWER-303D
SWPP .certifications .are .signed .by .- .CORRECT .ANSWER-An .officer .of .the
.project .owner .or .an .officer .of .the .general .contractor.
TRUE .OR .FALSE: .The .document .that .must .be .completed .signed .and .submitted
.to .the .state .to .obtain .authorization .to .discharge .is .the .NOT .- .CORRECT
.ANSWER-False
The .notice .of .termination .can .be .filed .when .- .CORRECT .ANSWER-All
.construction .inside .and .outside .of .the .building .is .completed .and .the .final
.stabilization .has .been .verified .as .complete
Operators .on .a .construction .site .are .the .entity .in .charge .of .plans .and
.specifications .and .the .entity .who .is .- .CORRECT .ANSWER-Is .in .charge .of .daily
.activities
You .should .have .a .SWPPP .for .your .construction .site .because .(3 .reasons) .-
.CORRECT .ANSWER-1. .Its .documents .stormwater .management .
2. .Demonstrates .your .intent .to .manage .stormwater .on .your .site .
https://www.stuvia.com/user/Mboffin
, 3. .It .is .required .by .law
https://www.stuvia.com/user/Mboffin