... Ans✓✓✓ certainty
"Critical" Breach Ans✓✓✓ In addition to notification and SAR, the
USD(AT&L) shall: Conduct root cause analysis and Assess costs
"Critical" Breach Ans✓✓✓ Increase of 25% from the current baseline
or 50% from the original baseline estimate
"Significant" Breach Ans✓✓✓ Increase of 15% from the current
baseline estimate or 30% from the original baseline estimate
"Significant" Breach Ans✓✓✓ Service Secretary notifies Congress
within 45 days of unit cost report (e.g., program deviation report)
Acquisition Program Baseline Ans✓✓✓ a formal agreement created
and signed by the Program Manager and those in the chain of authority
up to the Milestone Decision Authority (MDA)
Acquisition Program Baseline sets the program's threshold and objective
parameters in three categories Ans✓✓✓ Performance; Schedule; Cost
Actions If Program Is Terminated Ans✓✓✓ Secretary will submit a
report to Congress stating: (1) An explanation of the reasons for
terminating the program, (2) The alternatives considered to address any
problems in the program, and (3) How the DoD plans to meet any