Post-test UPDATED ACTUAL Exam
Questions and CORRECT Answers
Prioritize types of controls from most preferred too least preferred. - CORRECT
ANSWER - Engineering , administrative, physical.
Identifying risks as early as possible is part of what Risk Management principle? - CORRECT
ANSWER - Anticipate and manage risk by planning.
Taking a risk that will not contribute to the task or mission accomplishment or will needlessly
jeopardize personnel or material goes against when Risk Management principle? - CORRECT
ANSWER - Accept no unnecessary risk.
You are at the beach. Looking up, your see a sign that says, "Hazardous Marine Life. Swim at
Your Own Risk." ...Based on Risk Management principles and using the Risk Management
process, how would you approach the idea of going for a swim now? - CORRECT
ANSWER - Evaluate the situation to determine if the wire fence physical control will have
the desire effect of mitigating the hazard to an acceptable level.
Designing a quiet generator to reduce the amount of hazardous noise is an example of what type
of risk control? - CORRECT ANSWER - Engineering
A(n) _______ is defined as any real or potential condition that can cause injury, illness, or death
to personnel; damage to or loss of equipment or property; degradation of mission capability or
impact to mission accomplishment; or damage to the environment. - CORRECT
ANSWER - hazard
A battalion commander and here staff are conducting a Marine Corps Planning Process (MCPP)
session to develop an operations order (OPORD) for an upcoming offensive operation. The
operation begins in 96-hours. The MCPP session would fall under with Risk Management level?
- CORRECT ANSWER - Deliberate