Section 1: Introduction
This document features fully verified and correct questions and answers for the Construction
Quality Management for Contractors (CQM-C) certification exam, updated for 2025/2026. It
covers quality control plans, contractor responsibilities, submittals, deficiency tracking, and
Army Corps/NAVFAC procedures. Graded A+ and aligned with actual exam standards.
Section 2: Exam Questions and Answers
Four answer choices per question (A–D)
Correct answer highlighted
1. The purpose of Construction Quality Management is to:
(a) Minimize project costs
(b) Achieve quality established by requirements
(c) Speed up construction timelines
(d) Reduce contractor oversight
ANS: Achieve quality established by requirements
Explanation: Focuses on meeting planned quality standards.
2. Construction Quality Management ensures construction is performed:
(a) With minimal supervision
(b) According to plans and specifications
(c) Using the cheapest materials
(d) Without safety protocols
ANS: According to plans and specifications
Explanation: Adheres to contract requirements.
3. Partnering relationships are based upon:
(a) Competitive bidding
(b) Building trust and common goals
(c) Reducing government involvement
(d) Maximizing individual profits
ANS: Building trust and common goals
Explanation: Emphasizes collaboration.
, 4. It is the responsibility of Quality Assurance Personnel to:
(a) Perform all construction tasks
(b) Periodically verify the contractor’s control system
(c) Design the project plans
(d) Handle financial payments
ANS: Periodically verify the contractor’s control system
Explanation: Ensures effective quality control.
5. An effective contractor quality control program will:
(a) Delay project completion
(b) Incentivize correct work the first time
(c) Increase overhead costs
(d) Eliminate safety measures
ANS: Incentivize correct work the first time
Explanation: Promotes efficiency and profit.
6. The success or failure of contractors is based upon:
(a) Government funding levels
(b) Ability to control costs and maintain quality
(c) Number of employees
(d) Project location
ANS: Ability to control costs and maintain quality
Explanation: Key to operational success.
7. Quality Assurance Personnel have the responsibility to:
(a) Build the project structures
(b) Require contractors to maintain specified quality
(c) Approve all submittals
(d) Manage the construction schedule
ANS: Require contractors to maintain specified quality
Explanation: Ensures contract compliance.
8. Inspection is:
(a) The design of construction plans
(b) The process of examining ongoing and completed work
(c) The approval of budgets
(d) The training of workers