High traffic volume from 7:00 am to 9:00 pm - ANSWER-What
might be a condition that would indicate a resurfacing project
may need to be done at night?
low traffic volumes at all times - ANSWER-What might be a
condition that would
indicate a resurfacing project should not be done at night
unless absolutely
necessary?
work from 9:00 am to 4:00 pm and reopen the work area during
non-working hours - ANSWER-The traffic speed is 55 mph and
traffic volumes are very heavy during rush hours, but light at
other times. What would be a good plan?
1 mile - ANSWER-if resurfacing takes one day to complete 3/4
of a mile in one lane, what would be the approximate length of
the closure at any given time?
,6" increments - ANSWER-the dimensions of a signs may be
increased in ____
as specified in the
MUTCD
tort - ANSWER-a _____ in legal terminology is *Civil Wrong*
other than a beach
of contract for which a court will provide
a remedy
legal obligation - ANSWER-*Liability* for a tort means the
____________ to pay
monetary damages to the person injured or
damaged
fluorescent orange or green - ANSWER-flaggers shall always
wear a ______
vest or
jacket
retroreflective - ANSWER-for night flagging, all clothing and
equipment should
be
________
, on the open roadway - ANSWER-a flagger never stands:
18", 6" - ANSWER-________ is the min size of slow/stop
paddle wide with
letters at least ________
high
24", 36" - ANSWER-the standard red flag used for
(emergency) flagging is at
least _____ square and fastened to a
______" staff
illuminated - ANSWER-the nighttime flagging station should be:
1) never stand on
the open roadway
2) always face
on-coming
traffic
3) not mingle
with the
workers