2018 IRC Study Session 14 Gen. Plumbing Requirements and Fixtures Exam with correct question and answers 1. Testing of the building sewer may be accomplished with a minimum head of water with the ability to maintain such pressure for a minimum of . a. 8-foot, 10 minutes b. 8-foot, 15 minutes c. 10-foot, 10 minutes d. 10-foot, 15 minutes: D 2. When tested by air upon completion of the rough piping installation, the DWV system shall be tested at or 10 inches of mer- cury column with the ability to maintain such pressure for a minimum of a. 5 psi, 10 minutes b. 5 psi, 15 minutes c. 10 psi, 10 minutes d. 10 psi, 15 minutes: B