It is up to the __ to conduct a preconstruction meeting , while it can fall on the ___ to require
one . - ANS-RDP , Building Official
When considering a special inspection firm for a project , the owner should evaluate : - ANS-All
of the above
Special inspectors become approved in a jurisdiction by - ANS-following the requirements of
the jurisdiction over the project
The statement of special inspections can address all of the following except : - ANS-What QC
manual is in place for a non - approved fabricator ?
Discussions about the frequency of reporting from the SIA ( special inspection agency ) should
be handled ultimately with - ANS-the building department , to understand how frequently they
want to receive and review the reporting and to whom the reports should go as the project
contact .
According to the International Building Code , there are four Risk Categories which any building
will fall under . Which of the following statements are true ? - ANS-A building with a higher risk
to life safety will require more inspection .
Alternate materials not originally designed or prescribed in the code are permitted for use on a
project , provided the material is not less in equivalence in all of the following aspects except -
ANS-longevity
According to the Special Inspection Manual , a manufacturer who wants to use a new or
alternate product than what has been prescribed by the IBC , will typically apply for an
evaluation report if the product has been available for ___ or more years . - ANS-5
According to the Special Inspection Manual , quality control differs from quality assurance in that
- ANS-quality control refers to procedures completed during the manufacturing of a product to
ensure a specified level of quality is in place , while quality assurance refers to the verification
by a third - party agency of a product's compliance .
ANSWERS 2025/2026 A+ GRADED 100%
VERIFIED
It is up to the __ to conduct a preconstruction meeting , while it can fall on the ___ to require
one . - ANS-RDP , Building Official
When considering a special inspection firm for a project , the owner should evaluate : - ANS-All
of the above
Special inspectors become approved in a jurisdiction by - ANS-following the requirements of
the jurisdiction over the project
The statement of special inspections can address all of the following except : - ANS-What QC
manual is in place for a non - approved fabricator ?
Discussions about the frequency of reporting from the SIA ( special inspection agency ) should
be handled ultimately with - ANS-the building department , to understand how frequently they
want to receive and review the reporting and to whom the reports should go as the project
contact .
According to the International Building Code , there are four Risk Categories which any building
will fall under . Which of the following statements are true ? - ANS-A building with a higher risk
to life safety will require more inspection .
Alternate materials not originally designed or prescribed in the code are permitted for use on a
project , provided the material is not less in equivalence in all of the following aspects except -
ANS-longevity
According to the Special Inspection Manual , a manufacturer who wants to use a new or
alternate product than what has been prescribed by the IBC , will typically apply for an
evaluation report if the product has been available for ___ or more years . - ANS-5
According to the Special Inspection Manual , quality control differs from quality assurance in that
- ANS-quality control refers to procedures completed during the manufacturing of a product to
ensure a specified level of quality is in place , while quality assurance refers to the verification
by a third - party agency of a product's compliance .