, Define NPIAS - ANS National Plan of Integrated Airport Systems
Large Hub - ANS Over 1% of total US enplanements
Medium Hub - ANS Between .25% and 1%
A
Small hub - ANS Between .05% and .25%
R
NonHub primary airport - ANS less than .05% but more than 10,000 annual enplanements
GA Airport: National - ANS Serves National & Global: High level of traffic. Average 200
total aircraft including 30 jets (Many jets)
U
GA Airport: Regional - ANS Serves Regional to National: High level of traffic. Average 90
total aircraft including 3 jets. (Some Jets)
LA
GA Airport: Local - ANS Serves Local: Moderate level of traffic. Average 33 total aircraft
(No Jets/Some multi engine prop)
GA Airport: Basic - ANS serving critical functions for local markets. Moderate to low traffic.
10 propeller based aircraft - no jets
C
Master plan time period - ANS 20 years
9 objects of master plan - ANS Document Issues. Justify the proposal through technical,
O
economic and environmental. provide graphic presentation of development. Establish a realistic
schedule. Achievable financial plan. Environmental evaluations. Plan addresses local, state and
federal regulations. Deliberations on future demand. Framework for continual planning.
D
Master plan will include: - ANS Pre-Planning. Public Involvement. Environmental
Considerations. Existing conditions. Aviation Forecasts. Facility requirements. Alternatives.
Airport Layout plan. Facilities implementation plan. Financial Feasibility analysis.
Five Deliverables of Master Plan - ANS Technical report. Summary Report. Airport Layout
plan. Web page. Public Info Kit
ALP - ANS Airport Layout Plan - initial and all changes must be approved by the FAA