AATC EXAM 1 QUESTIONS AND ANSWERS
1. DOD relies on a combination of these three entities for the development of S&T to incorporate -3
legged stool - CORRECT ANSWER✅✅✅Industry, DoD, org and universities
1. This center uses a broad charter for the purpose of performing, analyzing - CORRECT
ANSWER✅✅✅FFRDC
1. CAIV also known as affordability, is about using cost to make these tradeoffs to keep weapon systems
affordable - CORRECT ANSWER✅✅✅Performance trade-offs
The AC strategy is based on information from the __ such as functional areas, range of military -
CORRECT ANSWER✅✅✅ICD
The procurement cost combines these two costs - CORRECT ANSWER✅✅✅Weapons and flyaway
costs
The adaptive AC frameworks and six pathways are managed by - CORRECT ANSWER✅✅✅DoD 5000
series
The purpose of this phase is to develop, build and test a system to verify that all operation and implied
requirements are met - CORRECT ANSWER✅✅✅EMD phase
Scrub budget year to prepare the defensible and detailed BES which culminates with the the issuance of
a resource management decision - CORRECT ANSWER✅✅✅Budgeting
This metrics is one of the statutory milestone decision information for a major capability acquisition
program - CORRECT ANSWER✅✅✅Risk
The MDA of the program has been briefed that a new capability which has a CDD-V with a technical
readiness level assessment of 6 - CORRECT ANSWER✅✅✅Milestone B
, Components develop a POM IAW with the DPG, turns the DPG into achievable & FYDP - CORRECT
ANSWER✅✅✅Programming
These appropriation categories are needed for a product improvement programs (PIP) which increase
performance system - CORRECT ANSWER✅✅✅RDT&E, procurement, O&M
___allows program to make predictions about futures - CORRECT ANSWER✅✅✅Escalation and
budgeting
Time period that you can use expired funds - CORRECT ANSWER✅✅✅5 years
When providing a reclama to a proposed program funding the program - CORRECT
ANSWER✅✅✅Objective and simple language
What does PPBE stand for - CORRECT ANSWER✅✅✅Planning, Programming, Budgeting, and
Execution
The two exception to the full funding policy are - CORRECT ANSWER✅✅✅Multiyear and
procurement
The production an deployment phase will require the following type of funding - CORRECT
ANSWER✅✅✅RDT&E, procurement, O&M
When the procuring contracting officer signs a contract a/an is created and the govt is legally liable to
pay for it - CORRECT ANSWER✅✅✅Obligation
__ permits the use of funds for other purposes not intended by congress at the time originally
appropriated - CORRECT ANSWER✅✅✅Reprogramming
The __ needs to verify that the appropriate amount of funding is available and in the correct appropriate
category before executing a contract modification based on the program managers - CORRECT
ANSWER✅✅✅KO
1. DOD relies on a combination of these three entities for the development of S&T to incorporate -3
legged stool - CORRECT ANSWER✅✅✅Industry, DoD, org and universities
1. This center uses a broad charter for the purpose of performing, analyzing - CORRECT
ANSWER✅✅✅FFRDC
1. CAIV also known as affordability, is about using cost to make these tradeoffs to keep weapon systems
affordable - CORRECT ANSWER✅✅✅Performance trade-offs
The AC strategy is based on information from the __ such as functional areas, range of military -
CORRECT ANSWER✅✅✅ICD
The procurement cost combines these two costs - CORRECT ANSWER✅✅✅Weapons and flyaway
costs
The adaptive AC frameworks and six pathways are managed by - CORRECT ANSWER✅✅✅DoD 5000
series
The purpose of this phase is to develop, build and test a system to verify that all operation and implied
requirements are met - CORRECT ANSWER✅✅✅EMD phase
Scrub budget year to prepare the defensible and detailed BES which culminates with the the issuance of
a resource management decision - CORRECT ANSWER✅✅✅Budgeting
This metrics is one of the statutory milestone decision information for a major capability acquisition
program - CORRECT ANSWER✅✅✅Risk
The MDA of the program has been briefed that a new capability which has a CDD-V with a technical
readiness level assessment of 6 - CORRECT ANSWER✅✅✅Milestone B
, Components develop a POM IAW with the DPG, turns the DPG into achievable & FYDP - CORRECT
ANSWER✅✅✅Programming
These appropriation categories are needed for a product improvement programs (PIP) which increase
performance system - CORRECT ANSWER✅✅✅RDT&E, procurement, O&M
___allows program to make predictions about futures - CORRECT ANSWER✅✅✅Escalation and
budgeting
Time period that you can use expired funds - CORRECT ANSWER✅✅✅5 years
When providing a reclama to a proposed program funding the program - CORRECT
ANSWER✅✅✅Objective and simple language
What does PPBE stand for - CORRECT ANSWER✅✅✅Planning, Programming, Budgeting, and
Execution
The two exception to the full funding policy are - CORRECT ANSWER✅✅✅Multiyear and
procurement
The production an deployment phase will require the following type of funding - CORRECT
ANSWER✅✅✅RDT&E, procurement, O&M
When the procuring contracting officer signs a contract a/an is created and the govt is legally liable to
pay for it - CORRECT ANSWER✅✅✅Obligation
__ permits the use of funds for other purposes not intended by congress at the time originally
appropriated - CORRECT ANSWER✅✅✅Reprogramming
The __ needs to verify that the appropriate amount of funding is available and in the correct appropriate
category before executing a contract modification based on the program managers - CORRECT
ANSWER✅✅✅KO