Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

CFCM Full Test Study Guide || With Questions & Answers (100% Accurate)

Rating
-
Sold
-
Pages
39
Grade
A+
Uploaded on
14-05-2025
Written in
2024/2025

CFCM Full Test Study Guide || With Questions & Answers (100% Accurate) CFCM Full Test Study Guide || With Questions & Answers (100% Accurate) A cost is reasonable if, in its nature and amount, it does not exceed that which would be a. incurred by a prudent person in the conduct of competitive business. b. accrued by a prudent person in the conduct of competitive business. c. determined to be allowable by the CO. d. determined to be allocable by the CO. - ANSWER - a. incurred by a prudent person in the conduct of competitive business. FAR 31.201-3 What definition best describes alternative dispute resolution? a. Procedures used to resolve issues in controversy. b. Procedures voluntarily used to resolve issues in controversy. c. Procedures used for asserting and resolving claims. d. Procedures voluntarily used for asserting and resolving claims. - ANSWER - b. Procedures voluntarily used to resolve issues in controversy. FAR 33.214 The government's policy is to try to resolve all contractual issues in controversy by a. mutual agreement at the CO's level. b. bilateral agreement at the CO's level. c. mutual agreement at a level above the CO. d. unilateral agreement at the CO's level. - ANSWER - a. mutual agreement at the CO's level. FAR 33.204 After receiving the GAO's written notice that a protest has been filed, an agency must give notice a. of the protest to the contractor or all parties who appear to have a reasonable prospect of receiving an award. b. of the protest only to the prime contractor performing the work. c. of the protest to all parties who appear to have a reasonable prospect of receiving award and begin compiling the information necessary to report to the GAO. d. through a government-wide point of entry (GPE). - ANSWER - a. of the protest to the contractor or all parties who appear to have a reasonable prospect of receiving an award. FAR 33.104 Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require certification? a. No, because the claimed amount is less than $100,000. b. Yes, because the aggregate value of the claim exceeds $100,000. c. No, because the claimed amount is less than $500,000. d. Yes, because the aggregate value of the claim exceeds $500,000. - ANSWER - b. Yes, because the aggregate value of the claim exceeds $100,000. FAR 33.207(d) Protests may be filed with a. either the agency or the GAO. b. the agency, the GAO, or the U.S. Court of Claims. c. either the contracting officer or the U.S. Court of Federal Claims. d. Small Claims Court for awards under the SAT. - ANSWER - b. the agency, the GAO, or the U.S. Court of Claims. FAR 33.102

Show more Read less
Institution
CFCM - Certified Federal Contract Manager
Course
CFCM - Certified Federal Contract Manager

Content preview

CFCM Full Test Study
2025
Guide || With Questions
& Answers (100%
Accurate)




Conceptial Research |

, CFCM Full Test Study Guide || With
Questions & Answers (100% Accurate)
A cost is reasonable if, in its nature and amount, it does not exceed that which would be

a. incurred by a prudent person in the conduct of competitive business.
b. accrued by a prudent person in the conduct of competitive business.
c. determined to be allowable by the CO.
d. determined to be allocable by the CO. - ANSWER - a. incurred by a prudent person
in the conduct of competitive business.

FAR 31.201-3

What definition best describes alternative dispute resolution?

a. Procedures used to resolve issues in controversy.
b. Procedures voluntarily used to resolve issues in controversy.
c. Procedures used for asserting and resolving claims.
d. Procedures voluntarily used for asserting and resolving claims. - ANSWER - b.
Procedures voluntarily used to resolve issues in controversy.

FAR 33.214

The government's policy is to try to resolve all contractual issues in controversy by

a. mutual agreement at the CO's level.
b. bilateral agreement at the CO's level.
c. mutual agreement at a level above the CO.
d. unilateral agreement at the CO's level. - ANSWER - a. mutual agreement at the CO's
level.

FAR 33.204

After receiving the GAO's written notice that a protest has been filed, an agency must
give notice

a. of the protest to the contractor or all parties who appear to have a reasonable
prospect of receiving an award.
b. of the protest only to the prime contractor performing the work.
c. of the protest to all parties who appear to have a reasonable prospect of receiving
award and begin compiling the information necessary to report to the GAO.
d. through a government-wide point of entry (GPE). - ANSWER - a. of the protest to the
contractor or all parties who appear to have a reasonable prospect of receiving an
award.

,FAR 33.104

Does a $75,000 claim resulting from a reduction of $350,000 and an increase of
$275,000 require certification?

a. No, because the claimed amount is less than $100,000.
b. Yes, because the aggregate value of the claim exceeds $100,000.
c. No, because the claimed amount is less than $500,000.
d. Yes, because the aggregate value of the claim exceeds $500,000. - ANSWER - b.
Yes, because the aggregate value of the claim exceeds $100,000.

FAR 33.207(d)

Protests may be filed with

a. either the agency or the GAO.
b. the agency, the GAO, or the U.S. Court of Claims.
c. either the contracting officer or the U.S. Court of Federal Claims.
d. Small Claims Court for awards under the SAT. - ANSWER - b. the agency, the GAO,
or the U.S. Court of Claims.

FAR 33.102

Who can authorize continued performance in the face of a protest after award?

a. the chief of the contracting office
b. the CO, provided his findings are documented in the file.
c. the head of the contracting activity.
d. the commanding officers. - ANSWER - c. the head of the contracting activity.

FAR 33.104(c)(2)

The CO shall consider all protests and seek legal advice

a. only if protests are received after award and filed directly with the agency.
b. only if the protest is received after award and filed directly with the GAO.
c. whether protests are submitted before or after award.
d. whether protests are submitted before or after award and whether filed directly with
the GAO, the U.S Court of Claims, or the agency. - ANSWER - d. whether protests are
submitted before or after award and whether filed directly with the GAO, the U.S Court
of Claims, or the agency.

FAR 33.102

Which of the following statements is NOT true?

, a. The government encourages the maximum practicable commercial use of inventions
made under government contracts.
b. The government recognizes rights in data developed at private expense, and limits its
demands for delivery of that data.
c. The government requires that contractors obtain permission from copyright owners
before including copyrighted works, owned by others, in data to be delivered to the
government.
d. Generally, the government will refuse to award a contract on the grounds that the
prospective contractor may infringe a patent. - ANSWER - d. Generally, the government
will refuse to award a contract on the grounds that the prospective contractor may
infringe a patent.

FAR 27.102

Performance and payment bonds are required or may be required for

a. construction contracts and services and supply contracts exceeding $2,000.
b. construction contracts exceeding $150,000.
c. any contract for services,
d. construction contracts exceeding $150,000 and services and supply contracts
exceeding the SAT when necessary to protect the governments interests. - ANSWER -
d. construction contracts exceeding $150,000 and services and supply contracts
exceeding the SAT when necessary to protect the governments interests.

FAR 28.102-1(a), 28.103-1(a), 28.103-2(a)

Cost Accounting Standards Board rules and regulations apply to

a. negotiated contracts and subcontracts.
b. sealed bid contracts.
c. contracts with small business concerns.
d. bridge contracts. - ANSWER - a. negotiated contracts and subcontracts.

FAR 30.000

The head of the agency may waive the applicability of Cost Accounting Standards
(CAS) for a particular contract or subcontract when one of these conditions exists:

a. The contract or subcontract is less than $50 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
b. The contract or subcontract is less than $15 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
c. The contract or subcontract is less than $7.5 million, primarily engaged in the sale of
commercial items.

Written for

Institution
CFCM - Certified Federal Contract Manager
Course
CFCM - Certified Federal Contract Manager

Document information

Uploaded on
May 14, 2025
Number of pages
39
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • far conventions at s
$19.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Thumbnail
Package deal
Certified Federal Contracts Manager (CFCM) Exam Bundle || With Complete Questions & Answers (100% Accurate)
-
9 2025
$ 55.49 More info

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
conceptialresearchers Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
619
Member since
3 year
Number of followers
338
Documents
3735
Last sold
1 week ago
Conceptial Researchers

Have an Exam due? Worry not. Welcome to Conceptial Research; I do the research so you don't have to. Here, you'll find verified study materials for your exams, quizzes, assignments, and general school work. All answers and papers here are graded A+ so you're guaranteed the best grades. I am also very friendly and approachable, so feel free to send a message in case you have a query. Please remember to leave a review if my study material are helpful. All the best.

Read more Read less
3.9

132 reviews

5
68
4
20
3
18
2
11
1
15

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions