Construction FE Civil Questions with Detailed Verified Answers (100% Correct Answers) /Already Graded A+

Rating
-
Sold
-
Pages
31
Grade
A+
Uploaded on
08-05-2025
Written in
2024/2025

Construction FE Civil Questions with Detailed Verified Answers (100% Correct Answers) /Already Graded A+

Institution
Construction FE Civil
Course
Construction FE Civil











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Construction FE Civil
Course
Construction FE Civil

Document information

Uploaded on
May 8, 2025
Number of pages
31
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

| OnlineExams | TestPrep | StudyResources | AcademicSuccess | ExamPreparation | QuizTime | LearningTools | Education | StudentSupport
In today's fast-paced educational landscape, students need reliable resources to excel in their studies.



5.0


Construction FE Civil Questions with Detailed
Verified Answers (100% Correct Answers) /Already
Graded A+
Is the most traditional project delivery method and appeals to those

looking for low-cost bids. In this method, the owner contracts designers

and builders separately.

Ans: Design-bid-build



is a construction project delivery method where the designer and

builder work together under a single contract from the beginning of the

project in order to ensure unity and collaboration throughout the

process.

Ans: Design- build



Select all that clearly demonstrate an advantage of the Design-Build

project delivery over the Design-Bid-Build approach:



- There is single point of contractual responsibility for the owner for the

entire project

-There are contractual relationships with the Owner that prevent a

conflict of interest

-The design is clearly and explicitly defined at the outset of the project




Sunday, 02 March 2025

,- The design includes significant collaboration between the Engineer

and the Contractor

-The schedule can be fast-tracked and construction can begin before

the complete project design is finalized

- The Owner will receive a project at the lowest competitive cost

Ans: There is single point of contractual responsibility for the owner for the
entire project


There is single point of contractual responsibility for the owner for the entire
project


The schedule can be fast-tracked and construction can begin before the
complete project design is finalized



An indemnification clause in an engineer's design contract is typically

tied to:



A. Negligent engineering design

B. Claims submitted by parties affected by a failure

C. Project cost overruns

D. Improper construction methods by the Contractor

Ans: A. Negligent engineering design




Examstudy - Stuvia US

,Collusion on a construction project typically refers to which of the

following?



A. A practice where multiple contractors conspire to fix prices or rig

bids

B. A system where public officials receive money from the contractor

after award

C. Falsely increasing the price of change order

D. Misrepresenting the amount of work that has been completed to get

advance payments

Ans: A. A practice where multiple contractors conspire to fix prices or rig
bids



A preconstruction conference should be he held:



A. Prior to advertising for bids

B. After advertising for bids but before bids are received

C. After bid opening but before award of the contract

D. After execution of an agreement but before Notice to Proceed

Ans: D. After execution of an agreement but before Notice to Proceed



Types of submittals for engineer approval typically include all the

following except:

Examstudy - Stuvia US

, A. Product data

B. Shop drawings

C. Installation means and methods

D. Mill certificates

Ans: C. Installation means and methods



Which of the following statements best define what is meant by

"substantial completion" with respect to a construction contract?



A. Project can be used and occupied by the owner and is completely

finished B. Project can be used and occupied by the owner but there is

still a punch-list of minor work remaining

C. Contractor's performance bond will be used to finish the remaining

work

D. The owner has received a final release of liens from all

subcontractors

Ans: B. Project can be used and occupied by the owner but there is still a
punch-list of minor work remaining



a financial guarantee that the terms of a contract will be honored. If

one party to a contract cannot complete their obligations, the bond is

paid out to the other party to compensate for their damages or costs.

Ans: Performance bond


Examstudy - Stuvia US

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Metric Yale School Of Medicine
View profile
Follow You need to be logged in order to follow users or courses
Sold
93
Member since
1 year
Number of followers
5
Documents
13109
Last sold
1 day ago

Welcome to Metric – Your Go-To Study Resource on Stuvia! At Metric, we believe studying should be smart, efficient, and effective. That’s why we offer high-quality, exam-ready study notes, summaries, and resources designed to help you understand key concepts faster and achieve better results. Whether you're cramming for finals, revising for a quiz, or looking to deepen your understanding, Metric provides content that’s clear, structured, and aligned with real course requirements. ✨ What you’ll find at Metric: ✔️ Accurate, in-depth summaries ✔️ Easy-to-follow formats for fast revision ✔️ Notes based on real syllabus & past exams ✔️ Regularly updated content you can trust Join hundreds of students who rely on Metric to study smarter—not harder. Browse the shop, grab what you need, and level up your academic game today!ades with Expert Academic Help

Read more Read less
3.0

12 reviews

5
3
4
1
3
2
2
5
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions