COSC 475 Test 2 2025 Questions and Answers 100% Pass Purpose of Scheduling - Determine - duration, critical activities, early start, late start Characteristics of Bar Chart Schedule - Horizontal chart; Illustrate start & finish dates of activities; Typically the dependency between activities is not shown; Easy to show current schedule status or % complete; Length corresponds to the duration of activity Another name for Bar Chart - Gantt Chart Schedule; Developed by Henry Gantt in 1910s Advantages of Bar Chart Schedule - Easy to present project tasks, durations, and anticipated start & finish dates; No special knowledge required; Suitable for small or simple projects; Created by scheduling software Disadvantages of Bar Chart Schedule - Typically do not show logic (relationships); Difficult to update schedule; 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED Difficult to determine the downstream effect of changes; Not suitable for long or large projects Bar Chart Preparation - Identify activities --> Estimate Durations --> Develop sequence --> Construct Bar Chart Identifying Activities - Activities that need to be accomplished in order to complete project; Extremely important because activities selected must encompass all of the required work to complete project; Will serve as basis for monitoring and controlling the work during construction Estimate Activity Duration - Based on available resources Develop Activity Sequence - Must take into account the four types of relationships; Relationships must be correctly incorporated into schedule Types of relationships - Physical, Safety, Resource,

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
5
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

COSC 475 Test 2 2025 Questions
and Answers 100% Pass


Purpose of Scheduling - ✔✔Determine - duration, critical activities, early start, late start

Characteristics of Bar Chart Schedule - ✔✔Horizontal chart;

Illustrate start & finish dates of activities;

Typically the dependency between activities is not shown;

Easy to show current schedule status or % complete;

Length corresponds to the duration of activity

Another name for Bar Chart - ✔✔Gantt Chart Schedule; Developed by Henry Gantt in
1910s

Advantages of Bar Chart Schedule - ✔✔Easy to present project tasks, durations, and
anticipated start & finish dates;

No special knowledge required;

Suitable for small or simple projects;

Created by scheduling software

Disadvantages of Bar Chart Schedule - ✔✔Typically do not show logic (relationships);

Difficult to update schedule;


COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, Difficult to determine the downstream effect of changes;

Not suitable for long or large projects

Bar Chart Preparation - ✔✔Identify activities --> Estimate Durations --> Develop
sequence --> Construct Bar Chart

Identifying Activities - ✔✔Activities that need to be accomplished in order to complete
project;

Extremely important because activities selected must encompass all of the required
work to complete project;

Will serve as basis for monitoring and controlling the work during construction

Estimate Activity Duration - ✔✔Based on available resources

Develop Activity Sequence - ✔✔Must take into account the four types of relationships;

Relationships must be correctly incorporated into schedule

Types of relationships - ✔✔Physical, Safety, Resource, Preferential

Construct a Bar Chart - ✔✔Use activity breakdown, durations, and planned sequence to
create

What are the Network diagramming methods - ✔✔AOA and AON

Activity On Arrow (AOA) - ✔✔Also known as Arrow Diagramming Method (AON) or
I-J Network;

Finish to Start Relationship only

Activity On Node (AON) - ✔✔Also known as Precedence Diagramming Method
(PDM)'

Uses four types of relationships - (FS, SS, FF, SF)



COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions