Cosc 475 Final Exam 2025 Questions and Answers 100% Pass crtical path - the longest continuous chain of activities through the network schedule that establishes the minimum overall project durations. Critical Path Characteristics - -Longest path through schedule -must have a start and end date -path is continuous through to the end of the schedule -Convergence: activities have more than one predecessor -Divergence: activities have more than one successor Early start / Early finish - Early Start (ES): The earliest an activity can be started after all predecessors to the activity are completed. Early Finish (EF): The earliest an activity can be finished given that activity's early start and duration. Late Start/late finish - Late Start (LS): The latest an activity can be started after all predecessors to the activity are completed. Late Finish (LF): The latest that an activity can be finished and still complete the project within the minimum overall duration determined by the forward pass. 2COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED Forward pass - the process of navigating through a network from start to end and calculating the early start and early finish dates for each activity and the finish date for the entire project. Goal: calculate the early start and finish dates Result: what is the total project duration? Backwards Pass - the process of navigating through a network from end to start and calculating the late start and finish dates. these dates determine the critical activities, critical path, and the amount of float each activity has. goal: determine the LS & LF dates for each activity result: what is the critical path of a project? Slack/Float - A number that indicates the amount of time a task can be delayed without impacting subsequent tasks or the project's overall completion. Task Slack = Late Start - Early Start Task Slack = Late Finish - Early Finish Most Owner contracts will dictate the duration of float that is required w

Show more Read less
Institution
COSC 475
Course
COSC 475









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
COSC 475
Course
COSC 475

Document information

Uploaded on
April 29, 2025
Number of pages
12
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Cosc 475 Final Exam 2025 Questions
and Answers 100% Pass


crtical path - ✔✔the longest continuous chain of activities through the network
schedule that establishes the minimum overall project durations.

Critical Path Characteristics - ✔✔-Longest path through schedule

-must have a start and end date

-path is continuous through to the end of the schedule

-Convergence: activities have more than one predecessor

-Divergence: activities have more than one successor

Early start / Early finish - ✔✔Early Start (ES): The earliest an activity can be started
after all predecessors to the activity are completed.

Early Finish (EF): The earliest an activity can be finished given that activity's early start
and duration.

Late Start/late finish - ✔✔Late Start (LS): The latest an activity can be started after all
predecessors to the activity are completed.

Late Finish (LF): The latest that an activity can be finished and still complete the project
within the minimum overall duration determined by the forward pass.




COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 1

, Forward pass - ✔✔the process of navigating through a network from start to end and
calculating the early start and early finish dates for each activity and the finish date for
the entire project.

Goal: calculate the early start and finish dates

Result: what is the total project duration?

Backwards Pass - ✔✔the process of navigating through a network from end to start and
calculating the late start and finish dates. these dates determine the critical activities,
critical path, and the amount of float each activity has.

goal: determine the LS & LF dates for each activity

result: what is the critical path of a project?

Slack/Float - ✔✔A number that indicates the amount of time a task can be delayed
without impacting subsequent tasks or the project's overall completion.

Task Slack = Late Start - Early Start

Task Slack = Late Finish - Early Finish




Most Owner contracts will dictate the duration of float that is required within the
schedule.

Preconstruction activities - ✔✔-linear process of getting an acceptable price

-Design activities

-Review of task list

-Procurement Activities

-Common Challenges (permits, cranes, community impact, etc)



COPYRIGHT © 2025 BY OLIVIA WEST, ALL RIGHTS RESERVED 2

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
OliviaWest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
109
Member since
1 year
Number of followers
17
Documents
8528
Last sold
1 week ago
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 reviews

5
6
4
2
3
4
2
1
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions