POPM Test, POPM Scaled Agile
Framework Sample Test 2025/2026 Exam
Questions and Answers | 100% Pass
By assigning business value - 🧠 ANSWER ✔✔How do Business Owners
quantify the value of PI Objectives?
Release stories that have been included in the team demo - 🧠 ANSWER
✔✔An ART has implemented a completely automated continuous
integration/continuous delivery (CI/CD) pipeline that can deploy code as it
is checked into the source code repository. How might a product owner
adjust team events to take advantage of this capability and promote the
flow of value?
It creates a clear understanding of when items are complete - 🧠 ANSWER
✔✔What is the importance of the Definition of Done?
Business Analysts & Subject Matter Experts - 🧠 ANSWER ✔✔Which two
jobs roles are good candidates for becoming a PO?
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
1
PRIVACY STATEMENT. ALL RIGHTS RESERVED
,Where the team has too much WIP - 🧠 ANSWER ✔✔When tracking team
progress what can a Kanban board show to the team?
How teams plan the implementation - 🧠 ANSWER ✔✔What does assigning
business value to the team's PI Objectives influence?
Look at the average story points completed from the last Iterations - 🧠
ANSWER ✔✔What is one way to establish a team's velocity?
Fictional characters that act as a representative user when discussing the
backlog - 🧠 ANSWER ✔✔What are personas?
Continuous Exploration and Release on Demand - 🧠 ANSWER ✔✔Which
two aspects of the Continuous Delivery Pipeline require the most
involvement from Product Managers?
Product Owners focus on the iteration while Product Managers focus on
the release - 🧠 ANSWER ✔✔Which statement characterizes the the
perspectives of the definition of done?
Split stories to eliminate dependencies & move stories on their team's
backlog to another team - 🧠 ANSWER ✔✔What are two strategies a PO
can use during PI Planning to minimize dependencies?
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
2
PRIVACY STATEMENT. ALL RIGHTS RESERVED
,less than 1 year - 🧠 ANSWER ✔✔What is the recommended time horizon
of the PI (Program Increment) roadmap?
Only during the Innovation and Planning iteration - 🧠 ANSWER ✔✔When
should innovation activities be conducted by teams on the ART?
Feature Toggles - 🧠 ANSWER ✔✔The goal is a fast delivery process,
ideally requiring little manual effort. What is one capability used to achieve
this?
Subtract one point for every team's member vacation day, public holiday, or
training day
Use eight points per person (adjust for time-part employees)
Find a small story that takes about a day to develop and call it a one - 🧠
ANSWER ✔✔An organization is conducting its first PI planning session,
and the new teams are asked to provide capacity. Which three actions are
part of the initial capacity planning process?
Feature estimates are rolled up into Epic estimates - 🧠 ANSWER ✔✔Which
statement is true about estimating and forecasting the portfolio backlog?
COPYRIGHT©PROFFKERRYMARTIN 2025/2026. YEAR PUBLISHED 2025. COMPANY REGISTRATION NUMBER: 619652435. TERMS OF USE.
3
PRIVACY STATEMENT. ALL RIGHTS RESERVED
, To manage queue length - 🧠 ANSWER ✔✔What is one-way Kanban's are
used in SAFe?
1-3 years - 🧠 ANSWER ✔✔What is the recommended time horizon for the
Solution Roadmap?
Iteration Retrospective - 🧠 ANSWER ✔✔Which Agile team event supports
relentless improvement?
Dependencies related to features
Dependencies between teams - 🧠 ANSWER ✔✔What two types of
dependencies are commonly visualized on the program board?
Backlog refinement
Daily Stand Up - 🧠 ANSWER ✔✔What are two examples of team level
events?
Product Management (PM) - 🧠 ANSWER ✔✔Which role is primarily
responsible for working with the business teams?
During PI Planning - 🧠 ANSWER ✔✔When should a PO establish team
objectives?