questions with verified answers
Only one quote was received in response to your competitive solicitation for
Government-unique tool kits that utilized the lowest price technically acceptable
source selection process. The quote, from Tool Warehouse, was determined to be
technically acceptable and was for a price of $124,500.
Which one of the following statements about the award decision is correct?
Ans✓✓✓
Six quotes were received in response to your solicitation for new office
equipment that utilized the lowest price technically acceptable source selection
process. The quotes submitted by vendors A, B, and D were determined to be
technically acceptable.
Vendor A quoted a price of $146,500;Vendor B quoted a price of $128,250; and
Vendor D quoted a price of $132,800.
Which one of the following statements about the award decision is correct?
Ans✓✓✓ Vendor B is the apparent awardee and price reasonableness would be
based on competition
Take 13 Ans✓✓✓ take 13
Three quotes were received in response to your solicitation for training services.
Evaluation was based on a tradeoff between price and past performance. The
assigned past performance ratings and quoted prices were as follows:
Vendor A - Unacceptable, $216,150;
Vendor B - Acceptable, $248,500; and
,Vendor C - Outstanding, $237,200.
Which one of the following statements about the award decision is correct?
Ans✓✓✓ Not - Vendor B is the apparent awardee and price reasonableness
could be based on any reasonable basis
Not - Vendor A is the apparent awardee and price reasonableness would be based
on competition.Vendor
Which one of the following is correct regarding documenting the award of a buy
using SAP? Ans✓✓✓ Not - Award documentation must be extensive and detailed
Not - Records of oral price quotations are not required
.
Which one of the following is NOT a mandatory Government source for satisfying
a supply requirement? Ans✓✓✓ Not - Excess from other agencies
not- services listed on federal
Which one of the following is NOT correct regarding documenting the award of a
buy using SAP? Ans✓✓✓ Maybe not - Records of oral price quotations must be
established to clearly reflect the appropriateness of the award decision.
Not - Price reasonableness should be based on competitive quotes or offers
whenever possible.
, A statement of price reasonableness is not required when only one quote or offer
is received.
Which one of the following is NOT one of the first steps taken when quotations
are received in response to a solicitation using SAP? Ans✓✓✓ documenting the
quotations
not- documenting the date and time the quotations are recieved
Which one of the following mandatory Government sources is the first priority for
satisfying a requirement for services? Ans✓✓✓ Not - Federal Prison Industries
Not - The Procurement List maintained by The Committee for Purchase From
People Who Are Blind or Severely Disabled
not - services listed on federal supply schedules
inventories of the requiring agency
Which one of the following market research results would NOT support a
commerciality determination? Ans✓✓✓ The part sold to the general public
needs' extensive modifications not customarily available in the commercial
marketplace.
Which one of the following market research results would support a
commerciality determination? Ans✓✓✓ Not - sold to the general public