100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CON-367 Exam 2 Questions with correct Answers 2025/2026( A+ GRADED 100% VERIFIED).

Rating
-
Sold
-
Pages
4
Grade
A+
Uploaded on
13-04-2025
Written in
2024/2025

CON-367 Exam 2 Questions with correct Answers 2025/2026( A+ GRADED 100% VERIFIED).

Institution
CON-367
Course
CON-367








Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CON-367
Course
CON-367

Document information

Uploaded on
April 13, 2025
Number of pages
4
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • con 367 exam 2 questions

Content preview

CON-367 Exam 2
T/F Our textbook advises that the starting date of a project should not be the date of the
execution (signing) of the agreement. - ANS -True

Under what type of bond, the surety has an obligation to the owner for any additional costs to
complete the project due to the contractor's failure to comply with its contract requirements? -
ANS -Payment Bond

T/F Multiple-Peril Builder's Risk Insurance provides similar but broader coverage than the
Standard Builder's Risk policy - ANS -True

Bid bonds should preferably be in an amount equal to _____ percent of the bid price for the
project. - ANS -10%

T/F The contract documents should require that evidence of specified insurance be submitted at
the time of submitting the bid bond. - ANS -False

T/F The following events are in correct order: Bid Opening-Bid Award-Notice to Proceed-Signing
of Agreement - ANS -False

T/F In construction projects, owners have a direct contractual relationship with the
subcontractors. - ANS -False

T/F The utilization of a contractor quality control (CQC) representative is a requirement in
private construction projects. - ANS -False

Which one of the following is not one of the activities that can be performed after the award of
the contract? - ANS -Obtain and submit a Bid Bond

T/F According to our textbook, the Resident Project Representative should adopt a "firm but fair"
policy in assuring the compliance of the Contractor with the contract documents. - ANS -True

T/F An owner can suspend the work in a construction project due to unsuitable weather
conditions. - ANS -True

T/F Suspensions and extensions of time will necessitate the issuance of a formal change order.
- ANS -True

Which of the following is not a type of a mobilization cost incurred by the Contractor? - ANS
-Preparing the bid

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
AVERYSELLER Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
265
Member since
2 year
Number of followers
122
Documents
3112
Last sold
2 weeks ago

3.8

40 reviews

5
18
4
6
3
8
2
4
1
4

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions