,Contractors are required to certify that a
claim is made in good faith when submitting
any claim exceeding: - ANSWER-$100,000
Feedback: See FAR 33.207
Maximize the likelihood of Successful
Results - ANSWER-1. AR 1.102-4(e) states
that contracting officers "should take the
lead in encouraging business process
innovations and ensuring that business
decisions are sound."
Facilitate Communications Among Affected
Parties - ANSWER-1. Effective
communication minimizes the effect of
personal biases, maximizes the likelihood
of successful results, and facilitates
communications among affected
stakeholders.
Cost, quality and timeliness of products and
services - ANSWER-1. FAR 1.102-2(a) tells
contracting professionals that a guiding
,principle is to satisfy customers in terms of
cost, quality, and timeliness of the delivered
product or service.
Contracting Officer Representative (COR) -
ANSWER-1. FAR 1.602-2(d)(7) states that
contracting officers shall designate CORs in
writing and furnish copies to the contractor
and the contract administration office
Standards of conduct - ANSWER-1. FAR
3.101-1 tells us Government business shall
be conducted in a manner above reproach
and, except as authorized by statute or
regulation, with complete impartiality and
with preferential treatment for none.
Methods of disseminating information -
ANSWER-1. For proposed contract actions
expected to exceed $25,000, by
synopsizing in theGovernment-wide Point
of Entry (GPE).For proposed contract
actions expected to exceed $15,000, but
, not expected to exceed$25,000. by
displaying in a public place.
Justification and Approval (J&A) - ANSWER-
2.FAR 6.303-1(a) states a contracting
officer shall not commence negotiations for
a sole source contract,commence
negotiations for a contract resulting from an
unsolicited proposal, or award any
othercontract without providing for full and
open competition unless the contracting
officer-
I. Justifies, if required in FAR 6.302, the use
of such actions in writing;
II. Certifies the accuracy and completeness
of the justification;
III. (and) Obtains the approval required by
FAR 6.304.
Post award orientation: - ANSWER-1. FAR
42.501(a) states a post award orientation
aids both Government and contractor
personnel to (1) achieve a clear and mutual
2025 Exam WITH
QUESTIONS AND
CORRECT
VERIFIED
ANSWERS GRADED
A+ guaranteed
100% pass
,Contractors are required to certify that a
claim is made in good faith when submitting
any claim exceeding: - ANSWER-$100,000
Feedback: See FAR 33.207
Maximize the likelihood of Successful
Results - ANSWER-1. AR 1.102-4(e) states
that contracting officers "should take the
lead in encouraging business process
innovations and ensuring that business
decisions are sound."
Facilitate Communications Among Affected
Parties - ANSWER-1. Effective
communication minimizes the effect of
personal biases, maximizes the likelihood
of successful results, and facilitates
communications among affected
stakeholders.
Cost, quality and timeliness of products and
services - ANSWER-1. FAR 1.102-2(a) tells
contracting professionals that a guiding
,principle is to satisfy customers in terms of
cost, quality, and timeliness of the delivered
product or service.
Contracting Officer Representative (COR) -
ANSWER-1. FAR 1.602-2(d)(7) states that
contracting officers shall designate CORs in
writing and furnish copies to the contractor
and the contract administration office
Standards of conduct - ANSWER-1. FAR
3.101-1 tells us Government business shall
be conducted in a manner above reproach
and, except as authorized by statute or
regulation, with complete impartiality and
with preferential treatment for none.
Methods of disseminating information -
ANSWER-1. For proposed contract actions
expected to exceed $25,000, by
synopsizing in theGovernment-wide Point
of Entry (GPE).For proposed contract
actions expected to exceed $15,000, but
, not expected to exceed$25,000. by
displaying in a public place.
Justification and Approval (J&A) - ANSWER-
2.FAR 6.303-1(a) states a contracting
officer shall not commence negotiations for
a sole source contract,commence
negotiations for a contract resulting from an
unsolicited proposal, or award any
othercontract without providing for full and
open competition unless the contracting
officer-
I. Justifies, if required in FAR 6.302, the use
of such actions in writing;
II. Certifies the accuracy and completeness
of the justification;
III. (and) Obtains the approval required by
FAR 6.304.
Post award orientation: - ANSWER-1. FAR
42.501(a) states a post award orientation
aids both Government and contractor
personnel to (1) achieve a clear and mutual