ICC / UST Exam Questions And Answers
|Latest 2025 | Guaranteed Pass.
Corrosion Specialist - Answer✔designs and certifies cathodic protection system
Secondary containment shall be constructed to contain at least the following volumes: -
Answer✔A. 100% of usable capacity of primary where there is only one primary is within the
secondary
B. 150% of the largest container if there are multiple primary containers in a single secondary
Cathodic protection tester will test cathodic protection system within __ months of installation
and every __ years thereafter - Answer✔6 months
3 years
Spill container shall meet the following requirements: - Answer✔A. If made of metal, exterior
wall shall be protected from galvanic corrosion
B. Shall have minimum capacity of 5 gallons (19 L)
C. Shall have drain valve which allows drainage of the collected spill into the primary container
or provide means to keep spill cont empty
Overfill prevention shall alert transfer operator when tank is __% full - Answer✔90%
1|P a g e
, ©BRIGHTSTARS 2025 ALL RIGHTS RESERVED 11:22 AM A+
Flapper Valves shall provide positive shut off when tank is filled to no more than __% capacity -
Answer✔95%
Primary pressurized piping shall be tested for tightness hydrostatically at __% of design
operating pressure - Answer✔150%
Date that all UST systems must have Line Leak Detector installed - Answer✔November 9,2004
Secondary containment testing shall be done upon ____, __months, and every ___ months or
____ years thereafter - Answer✔Installation
6 months
36 months or 3 years
Owners/ops shall submit SCT results to local agency within ____ days of completion -
Answer✔30 days
All monitoring equipment shall be tested, calibrated, operated, maintained, and certified every
____ months. - Answer✔12 months
A person conducting UST monitoring equipment certification shall affix tag/sticker on each
component and shall include ___ and ___. - Answer✔Date certified, replaced or repaired
Contractor/tank tester's license number
LLD shall detect release of __ gph and ___ PSI within ___ hour - Answer✔3 gph
10 PSI
Suction piping shall be tested every ___ years - Answer✔3 years
2|P a g e