Answers 100% Pass
Project Delivery Methods - ✔✔- Design-Bid-Build
- Design-Build
- CM
- Multiple Prime
Contract Types - ✔✔- lump sum
- unit price
- cost plus
Liquidated damages - ✔✔Contractually stipulated amount to be paid for
particular breach of contract
Bid bond - ✔✔guarantee bidder will enter into contract with client if lowest
bidder
1
Katelyn Whitman, All Rights Reserved © 2025
, Performance bond - ✔✔guarantees contractor will perform specified work
Payment bond - ✔✔guarantees contractor will pay for materials/labor
used
Surety bond - ✔✔Assumes liability for debt, default, failure in duty of
another party
Mechanic's Lien - ✔✔legal right to lay claim to project property until paid
Cohesionless soils - ✔✔sands/gravels
Cohesive soils - ✔✔clays/silts
(internal friction angle = 0)
Normally consolidated - ✔✔present effective overburden pressure is
maximum
Differential settlements - ✔✔most damaging, not uniform across supported
area
Geotech testing - ✔✔- Atterberg Limits (Shrinkage Limit Test)
- Standard Proctor Test
2
Katelyn Whitman, All Rights Reserved © 2025