A project is said to be temporary because: A. it has a short duration B. it has a definite beginning and end C. it has the potential to be a continuous and ongoing effort D. its project team outlives it. - ANSWERB. it has a definite beginning and end Which of the following is NOT a characteristic of a project? A. Constrained by limited resources B. Creates unique product or services C. Ongoing and repetitive D. Planned, executed, and controlled - ANSWERC. Ongoing and repetitive Project deliverables may be: A. overall quality B. the functional team C. agendas D. products or services. - ANSWERD. products or services. _________ management ensures the project includes all the specified work required, and ONLY the specified work, which is necessary to successfully complete the project. A. Project B. Scope C. Control D. Risk - ANSWERB. Scope In the scope statement, the project manager includes: A. Project objectives and deliverables B. Estimated project costs C. A detailed project phase schedule D. A project team directory for stakeholders. - ANSWERA. Project objectives and deliverables During Collect Requirements, the project manager should consider A. how the scope activity will be managed B. The scope of the deliverables C. customer expectations D. Product scope. - ANSWERC. customer expectations The project scope is defined as: A. the degree of stakeholder involvement B. the work to be done C. plan creation D. the project's specified needs. - ANSWERB. the work to be done What activities are involved in scope management? A. estimating B. executing C. defining D. all of the above - ANSWERC. defining _______ states in detail what needs to be done. A. Project verification B. The project charter C. The project scope statement D. Work breakdown templates - ANSWERC. The project scope statement In the context of the project, product scope refers to: A. the product characteristics B. t Project deliverables may be: A. overall quality B. the functional team C. agendas D. products or services. - ANSWERD. products or services. _________

Show more Read less
Institution
PMBOK 6 CAPM
Course
PMBOK 6 CAPM









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PMBOK 6 CAPM
Course
PMBOK 6 CAPM

Document information

Uploaded on
February 28, 2025
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • pmbok 6 capm

Content preview

PMBOK 6 CAPM Practice Questions &
Answers 100% Correct
A project is said to be temporary because:
A. it has a short duration
B. it has a definite beginning and end
C. it has the potential to be a continuous and ongoing effort
D. its project team outlives it. - ANSWERB. it has a definite beginning and end

Which of the following is NOT a characteristic of a project?
A. Constrained by limited resources
B. Creates unique product or services
C. Ongoing and repetitive
D. Planned, executed, and controlled - ANSWERC. Ongoing and repetitive

Project deliverables may be:
A. overall quality
B. the functional team
C. agendas
D. products or services. - ANSWERD. products or services.

_________ management ensures the project includes all the specified work
required, and ONLY the specified work, which is necessary to successfully complete
the project.
A. Project
B. Scope
C. Control
D. Risk - ANSWERB. Scope

In the scope statement, the project manager includes:
A. Project objectives and deliverables
B. Estimated project costs
C. A detailed project phase schedule
D. A project team directory for stakeholders. - ANSWERA. Project objectives and
deliverables

During Collect Requirements, the project manager should consider
A. how the scope activity will be managed
B. The scope of the deliverables
C. customer expectations
D. Product scope. - ANSWERC. customer expectations

The project scope is defined as:
A. the degree of stakeholder involvement
B. the work to be done
C. plan creation
D. the project's specified needs. - ANSWERB. the work to be done

, What activities are involved in scope management?
A. estimating
B. executing
C. defining
D. all of the above - ANSWERC. defining

_______ states in detail what needs to be done.
A. Project verification
B. The project charter
C. The project scope statement
D. Work breakdown templates - ANSWERC. The project scope statement

In the context of the project, product scope refers to:
A. the product characteristics
B. the product functions
C. required work to accomplish end deliverables
D. all of the above. - ANSWERD. all of the above.

The project manager uses product and stakeholder analyses, expert judgment, and
alternatives identification during the process of
A. Collect Requirements
B. Define Scope
C. Validate Scope
D. Create WBS - ANSWERB. Define Scope
Systems are
A. linear in responsiveness
B. dynamic
C. static
D. limited to programs - ANSWERB. dynamic

Enterprise Environmental Factors can be
A. internal only
B. external only
C. both internal and external
D. neither internal or external - ANSWERC. both internal and external

Internal enterprise environmental factors include
A. legal restrictions
B. infrastructure
C. academic research
D. financial considerations - ANSWERB. infrastructure


Directing and managing project work is the integrative process that performs
activities outlined in the
A. WBS
B. project scope statement
C. project charter
D. SOW. - ANSWERB. project scope statement

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
nursingismylife West Virginia University
View profile
Follow You need to be logged in order to follow users or courses
Sold
248
Member since
2 year
Number of followers
174
Documents
9127
Last sold
1 week ago

3.6

38 reviews

5
14
4
12
3
3
2
1
1
8

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions