1. On a steel tank without cathodic protection, if a coating b. Current flow is in-
is flawed, what happens at the flaw? creased from this area
a. Cathodic surface is increased
b. Current flow is increased from this area
c. Current flow is increased to this area
2. On an impressed current cathodic protection system, b. Cathode
the negative wire of the rectifier is connected to the:
a. Anode
b. Cathode
c. Drop tube
d. Dielectric union
3. All are examples of acceptable release detection for a. Impressed current ca-
tanks, except: thodic protection
a. Impressed current cathodic protection
b. Automatic tank gauging
c. Statistical inventory reconciliation
d. Soil-vapor monitoring
4. When a tank is temporarily closed, the cathodic protec- b. Must remain in opera-
tion system: tion
a. Must be turned off
b. Must remain in operation
c. Should be removed
d. Operator can have it on or off.
5. When a steel tank is installed with a galvanic CP sys- c. To electrically isolate the
tem attached, the tank gauges are usually connected tank from the tank gauge
through a riser with a dielectric bushing. What is the
purpose of that?
a. To prevent static discharge
, U3 ICC Tank Tightness Testing
Study online at https://quizlet.com/_8746hx
b. To minimize effects of noise
c. To electrically isolate the tank from the tank gauge
d. To prevent water intrusion in the tank
6. Factory-installed diectric coatings may include all of a . Asphalt
the following except:
a . Asphalt
b. epoxies
c. Enamels
d. fiberglass-reinforced plastic
7. According to the EPA, Tank tightness test data must be d. Until the next test is per-
maintained for: formed
a. 18 months
b. 3 years
c. 5 years
d. Until the next test is performed
8. How long must records of UST system repairs be avail- d. for the remaining life-
able on site? time of the UST system
a. 60 days
b. 1 year
c. 5 years
d. for the remaining lifetime of the UST system
9. In the event of a release, what is the reporting require- b. Owner/Operator must
ment? report the leak within 24
a. ICC licensed supervisor must report the leak within hours
24 hours
b. Owner/Operator must report the leak within 24
hours
c. Owner/Operator must report the leak within 18
hours