1. When creating an AON graph, you always draw
nodes all for which of its predecessor
activities have been completed.

2. The earliest completion time is the earliest start

time plus the activity time.
path
3. A is a sequence of nodes and arrows
within the activity network.
process
4. The completion time of individual activities is
most important in management.

5. The path is the path with the longest duration. critical

6. Click and drag on elements in order
Arrange the steps to compute the earliest
completion time (ECT) of the project.

7. Loops in an activity network indicate events.
interdependent

8. The earliest start time of the first activity is time . zero or 0

9. The duration of a path is calculated by up the adding,
summing, or to-
activity times of the activities that constitute that path. talling

10. time is the amount of time an activity can Slack
be de- layed without affecting the overall
completion time of the project.

11. Match the type of management with the
1. Bottleneck
activity that needs to be identified.
activity
1/
32

, TOM 3010 notes MOD 4 questions with verified solutions

2. Last activity completed




2/
32

, TOM 3010 notes MOD 4 questions with verified solutions

1. Process management
2. Project management

12. Select all that apply A2
A project consists of three tasks: A1,A2, and A3. A1

A1 must be completed before A3. Which activities
can start at time 0?

13. A project consists of three tasks: A1,A2, and
A3. A1

A1 must be completed before A3. There is an
arrow point- ing away from which node?

14. The slack time of an activity is based on the early start late
schedule and the start schedule.

15. The earliest start time for an activity is the earliest time predecessor
or preceding
all activities have been completed.

16. When computing the late start schedule, the latest
latest start time for an activity should be set
to the
completion time of the activity minus its
activity time.

17. Activities on the critical path have slack time. zero

18. The time of an activity can be calculated as activity.
Latest start time - Earliest start time.
20. When
19. The latest completion time of an activity is computing
based on the latest start times of of that the late
3/
32

, TOM 3010 notes MOD 4 questions with verified solutions

start schedule, the latest completion time for slack
an activity should be set to the latest start
time of all activities.
successors


dependent




4/
32

Document information

Uploaded on
January 30, 2025
Number of pages
32
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$18.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BukayoSaka120
3.7
(33)
Sold
112
Followers
72
Items
6117
Last sold
2 days ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions