100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

PROJECT MANAGEMENT CHAPTER 4 LATEST UPDATE WITH 58 QUESTIONS AND ACCURATE DETAILED ANSWERS GRADED A+

Rating
-
Sold
-
Pages
6
Grade
A+
Uploaded on
30-01-2025
Written in
2024/2025

PROJECT MANAGEMENT CHAPTER 4 LATEST UPDATE WITH 58 QUESTIONS AND ACCURATE DETAILED ANSWERS GRADED A+

Institution
PROJECT MANAGEMENT
Course
PROJECT MANAGEMENT









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PROJECT MANAGEMENT
Course
PROJECT MANAGEMENT

Document information

Uploaded on
January 30, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PROJECT MANAGEMENT CHAPTER 4 LATEST UPDATE
2025-2026 WITH 58 QUESTIONS AND ACCURATE
DETAILED ANSWERS GRADED A+

The approved project scope statement and its associated WBS and WBS
dictionary. -Correct Answer- scope baseline

The tendency for project scope to continually increase -Correct Answer-
scope creep

The amount of time an activity may be delayed without delaying a
succeeding activity or the project finish date. -Correct Answer- slack or
float

A document created to help promote teamwork and clarify team
communications. -Correct Answer- team contract

a management philosophy that states that nay complex system at any
point in time often has only one aspect or constraint that is limiting its
ability to achieve more of its goal. -Correct Answer- Theory of
Constraints (TOC)

An estimate that includes an optimistic, most likely, and pessimistic
estimate. -Correct Answer- three-point estimate

a deliverable-oriented grouping of the work involved in project that
defines the total scope of the project. -Correct Answer- work breakdown
structure(WBS)

a document that describes detailed information about WBS tasks. -
Correct Answer- work breakdown structure (WBS) dictionary

What can project teams create to help promote teamwork and clarify
team communications? -Correct Answer- a team contract

, The main purpose of project planning is to -Correct Answer- guide
project execution

Project teams develop a _________ to coordinate all other project plans
-Correct Answer- project management plan

a______________ is a deliverable-oriented grouping of the work
involved in a project that defines the total scope of the project. -Correct
Answer- WBS

A_____________is a task at the lowest leve of the WBS that represents
the level of work that the project manager uses to monitor and control
the project. -Correct Answer- Work package

What is the first step in planning a project schedule? -Correct Answer-
Developing an activity list

What is the most common type of dependency between activities? -
Correct Answer- finish to start

The ______method is a network diagramming technique used to predict
total project duration. -Correct Answer- critical path

What cost estimating technique uses project characteristics in a
mathematical model to estimate project costs? -Correct Answer-
parametric modeling

a_____________is a time-phased budget that project managers use to
measure and monitor cost performance -Correct Answer- Cost
performance baseline
Information that provides schedule-related information about each
activity, such as predecessors, successors, logical relationships, leads
$17.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
gmuthoni562
5.0
(1)

Get to know the seller

Seller avatar
gmuthoni562 teach me 2
View profile
Follow You need to be logged in order to follow users or courses
Sold
2
Member since
1 year
Number of followers
0
Documents
281
Last sold
1 year ago

5.0

1 reviews

5
1
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions