,Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers - ANSWER---
A201: 14.2.1
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
3- Architect
4- Supplier - ANSWER---A201: 1.5.1
Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of Servic
3- Architect
A Subcontractor's employee incorrectly performs the Work. Who is responsible (to the Owner)
for the error?
,1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor - ANSWER---A201: 3.3.2
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision shall be
required as a condition precedent to mediation of any Claim arising prior to the date final
payment is due, unless 30 days have passed after the Claim has been referred to the Initial
Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30 - ANSWER---A201: 15.2.1
Article 15) Claims and Disputes
15.2 Initial Decision
, 4- 30
The ____________ will on request furnish to a ____________ information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect - ANSWER---A201: 9.6.3
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect