Test Bank for CM 2311- Questions Fully Solved Latest Update What is a contract? - Answers Legally binding promise What are the primary ingredients of a contract? - Answers Something of value must be exchanged, mutual agreement between parties, capacity to understand the agreement, and the objects of the contract must be lawful. Why would it matter to a contractor if a project does not have the required building permits? - Answers Because the project can be stopped due to it being unlawful. Which cost money and time due to the delay What does it mean to breach a contract? - Answers Breaching a contract is not upholding the promises you made to another party that you had an agreement with. You signed an agreement with a friend to build an addition on his house. He was drunk when he signed the agreement. How might this cause problems if you ever have to take him to court for non-payment? - Answers Because the friend didn't have the capacity to agree to any terms. What is the primary distinguishing characteristic of the different contract types? - Answers Different risks and payments You are a contractor with a cost plus a fee contract and the project ends up costing $50,000 more than the budget. What is the impact on you? - Answers The contractor would get more money than anticipated due to the 5% fee coming out of actual cost, not the original cost. What type of contract is riskiest for the contractor? Why? - Answers Lump sum contract. What type of contract is generally used on small or formulaic projects? - Answers Lump sum contract. How does guaranteed maximum price reduce an owner's risk? - Answers The max price allows for a tight/fixed budget, which is less risky for the owner, because there won't be any surprise costs. What is the difference between bid documents and contract documents? - Answers Bid documents have bid forms, instructions to bidders, and bidder qualifications, but not change orders. Contract documents have change orders. What are included in contract documents? - Answers Agreement, drawings, specifications, general and supplementary conditions, and modifications. What is an agreement? - Answers Legally binds the parties, states terms of the project, and evidence of mutual agreement. Who is responsible for developing the bid documents? - Answers The owner of the project. What are the general conditions? - Answers General conditions define the terms and conditions for a project. On small projects, where might the general conditions be found? - Answers They may be written as notes on the construction drawings. Who is responsible for ensuring that the general conditions are included as part of the bid documents? - Answers The owner, architect, and contractor. Which construction document modifies the general conditions? - Answers Supplementary conditions are used to modify or expand the general conditions. Give a specific example of when supplementary conditions might be used. - Answers Supplementary conditions might be used to change a contractor's project site responsibilities such as limiting the time allowed for the project. What are the specifications? - Answers The drawings are a graphic representation of a project that show quantities of materials; they are insufficient alone for pricing and construction purposes. What does the CSI stand for and what is it? - Answers Construction Specification Institute How does the MasterFormat assist the contractor? - Answers MasterFormat helps the contractor by breaking down the details of a project to be examined more closely. What are four types of writing specifications and describe all of them? - Answers 1) Performance - Identifies the ends to be achieved, but not how the ends are archived.

Content preview

Test Bank for CM 2311- Questions Fully Solved Latest Update 2025-2026

What is a contract? - Answers Legally binding promise

What are the primary ingredients of a contract? - Answers Something of value must be exchanged,
mutual agreement between parties, capacity to understand the agreement, and the objects of the
contract must be lawful.

Why would it matter to a contractor if a project does not have the required building permits? - Answers
Because the project can be stopped due to it being unlawful. Which cost money and time due to the
delay

What does it mean to breach a contract? - Answers Breaching a contract is not upholding the promises
you made to another party that you had an agreement with.

You signed an agreement with a friend to build an addition on his house. He was drunk when he signed
the agreement. How might this cause problems if you ever have to take him to court for non-payment? -
Answers Because the friend didn't have the capacity to agree to any terms.

What is the primary distinguishing characteristic of the different contract types? - Answers Different
risks and payments

You are a contractor with a cost plus a fee contract and the project ends up costing $50,000 more than
the budget. What is the impact on you? - Answers The contractor would get more money than
anticipated due to the 5% fee coming out of actual cost, not the original cost.

What type of contract is riskiest for the contractor? Why? - Answers Lump sum contract.

What type of contract is generally used on small or formulaic projects? - Answers Lump sum contract.

How does guaranteed maximum price reduce an owner's risk? - Answers The max price allows for a
tight/fixed budget, which is less risky for the owner, because there won't be any surprise costs.

What is the difference between bid documents and contract documents? - Answers Bid documents have
bid forms, instructions to bidders, and bidder qualifications, but not change orders. Contract documents
have change orders.

What are included in contract documents? - Answers Agreement, drawings, specifications, general and
supplementary conditions, and modifications.

What is an agreement? - Answers Legally binds the parties, states terms of the project, and evidence of
mutual agreement.

Who is responsible for developing the bid documents? - Answers The owner of the project.

What are the general conditions? - Answers General conditions define the terms and conditions for a
project.

, On small projects, where might the general conditions be found? - Answers They may be written as
notes on the construction drawings.

Who is responsible for ensuring that the general conditions are included as part of the bid documents? -
Answers The owner, architect, and contractor.

Which construction document modifies the general conditions? - Answers Supplementary conditions are
used to modify or expand the general conditions.

Give a specific example of when supplementary conditions might be used. - Answers Supplementary
conditions might be used to change a contractor's project site responsibilities such as limiting the time
allowed for the project.

What are the specifications? - Answers The drawings are a graphic representation of a project that show
quantities of materials; they are insufficient alone for pricing and construction purposes.

What does the CSI stand for and what is it? - Answers Construction Specification Institute

How does the MasterFormat assist the contractor? - Answers MasterFormat helps the contractor by
breaking down the details of a project to be examined more closely.

What are four types of writing specifications and describe all of them? - Answers 1) Performance -
Identifies the ends to be achieved, but not how the ends are archived.

2) Descriptive - Provides product details without specifically mentioning a brand name.

3) Reference - Identifies a required standard such as ASTM, State of New York, Federal, and so on.

4) Proprietary. - Identifies the desired product by manufacturer, brand name, model, and so on.

How does a guaranteed maximum price reduce an owner's risk? - Answers The max price allows for a
tight/fixed budget, which is less risky for the owner, because there won't be any surprise costs.

What is the document that indicates the contractor can move onto the job site and begin work? -
Answers Notice to proceed

Why does it reduce a contractor's risk to begin construction only after receiving authorization from the
owner? - Answers Because if you start working before getting the notice to proceed from the owner,
you take the risk of not being reimbursed for start-up cost.

What purpose does insurance serve? - Answers It reduces the risk of loss or damages to the contractor,
to property, and to equipment from accidents.

What is the purpose of a job site layout plan? - Answers The purpose is to plan out the project to be able
to start work as soon as possible when awarded the bid.

Document information

Uploaded on
January 22, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$10.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh
3.4
(74)
Sold
474
Followers
16
Items
32574
Last sold
22 hours ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions