CON 367 Exam 2 Questions With Correct Answers 100% Guaranteed Pass. 5 Main steps in Bidding Phase - Answer1. Bid package preparation 2. Issuing invitaiton to bids 3. managing the bid cycle 4. Bid recipient and opening 5. Notice of intent of award Bid package preparation - Answerthe documents that are available to bidders EX: Drawings, specs, contracts, instructions to bidders etc. ** It is good practice to have a agency CM bid the package before sent out to GC's to find errors Issuing Invitation for Bids (IFB) - AnswerA advertisement to bid a project Includes bidding information - Bid Bond requirement - Prebid conference - Issue date Bidder Prequalification - AnswerOwners want to make sure that the contractor has the capacity and ability to complete the work Two main ways for of Prequalification - Answer1. Screening contractors before issuing the bid package 2. Contractor applies for prequalification. If accepted by owner the contractor needs to submit "prequalificaiton certificate" with its bid. 2 | P a g e Managing the Bid Cycle - AnswerMaking sure that the bid cycle is smooth for contractors. Prebid Conference: Explain technical aspects of the project as well as the supplementary conditions, bidders bring up potential problems such as inadequate bidding time. Site Visits Addenda Bid Receipt and opening - Answerin public projects this is a formal procedure set by regulation The procedure of submitting a bid for careful review Notice of intent to award - AnswerWhoever is awarded the bid. Usually the lowest price, responsible bidder Notice states that the bidder needs to furnish a performance Bonds - AnswerA financial obligation to assure payments will be made. Issued by a surety. Surety company thoroughly analyzes contractor before issuing them a bond. Provides a extra level of financial resource behind the contractor, a place the owner can turn to if the contractor cannot meet contractual agreements through their own assets Penal Sum - AnswerThe limit of a Surety's company liability under a bond. Tripartite relationship - AnswerPrincipal: Contractor Obligor : Surety Obligee: owner Bid Bond - AnswerThe obligation states that the principal will honor its bid. Performance Bond - Answerthe obligation stat

Show more Read less
Institution
CON 367
Course
CON 367









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CON 367
Course
CON 367

Document information

Uploaded on
January 16, 2025
Number of pages
10
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CON 367 Exam 2 Questions With Correct
Answers 100% Guaranteed Pass.


5 Main steps in Bidding Phase - Answer✔1. Bid package preparation
2. Issuing invitaiton to bids
3. managing the bid cycle
4. Bid recipient and opening
5. Notice of intent of award
Bid package preparation - Answer✔the documents that are available to bidders
EX: Drawings, specs, contracts, instructions to bidders etc.




** It is good practice to have a agency CM bid the package before sent out to GC's to find errors
Issuing Invitation for Bids (IFB) - Answer✔A advertisement to bid a project


Includes bidding information
- Bid Bond requirement
- Prebid conference
- Issue date
Bidder Prequalification - Answer✔Owners want to make sure that the contractor has the capacity
and ability to complete the work
Two main ways for of Prequalification - Answer✔1. Screening contractors before issuing the bid
package


2. Contractor applies for prequalification. If accepted by owner the contractor needs to submit
"prequalificaiton certificate" with its bid.


1|Page

, Managing the Bid Cycle - Answer✔Making sure that the bid cycle is smooth for contractors.


Prebid Conference:
Explain technical aspects of the project as well as the supplementary conditions, bidders bring up
potential problems such as inadequate bidding time.


Site Visits


Addenda
Bid Receipt and opening - Answer✔in public projects this is a formal procedure set by regulation


The procedure of submitting a bid for careful review
Notice of intent to award - Answer✔Whoever is awarded the bid. Usually the lowest price,
responsible bidder


Notice states that the bidder needs to furnish a performance
Bonds - Answer✔A financial obligation to assure payments will be made.


Issued by a surety. Surety company thoroughly analyzes contractor before issuing them a bond.


Provides a extra level of financial resource behind the contractor, a place the owner can turn to if
the contractor cannot meet contractual agreements through their own assets
Penal Sum - Answer✔The limit of a Surety's company liability under a bond.
Tripartite relationship - Answer✔Principal: Contractor
Obligor : Surety
Obligee: owner
Bid Bond - Answer✔The obligation states that the principal will honor its bid.

Performance Bond - Answer✔the obligation states that the principal will complete the project in
accordance with the project documents.




2|Page

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TheStar Florida State University
View profile
Follow You need to be logged in order to follow users or courses
Sold
595
Member since
1 year
Number of followers
178
Documents
23585
Last sold
7 hours ago
Stuvia Prodigy

Tested, Verified and Updated Study Materials with 100% Guaranteed Success.

3.8

119 reviews

5
56
4
21
3
21
2
4
1
17

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions