questions correctly answered already passed
What are the phases of the Project Life Cycle?
a. scope, budget, time
b. budget, plan, execution, close
c. define, plan, execution, close - correct answer ✔✔c. define, plan, execution, close
What is triple constraint?
a. scope, budget, schedule
b. define, plan, execute
c. balance, tradeoff, communication - correct answer ✔✔a. scope, budget, schedule
What is an example of information that might be found in a project proposal?
a. Low-level estimate of the costs
b. Project charter
c. Risks to the project - correct answer ✔✔c. risks to the project
A complete project proposal includes any risks that might derail the project.
What concludes the project defining phase? (Choose all that apply.)
a. Creation of the project charter
b. Creation of a work breakdown structure
, c. Selection of the project
d. Brainstorming approaches for getting key stakeholders on board - correct answer ✔✔a. Creation of
the project charter
c. Selection of the project
Major project outcomes and deliverables, how the project will be completed, and a high-level estimate
of the cost and completion time are included in the _____.
a. project concept document
b. project proposal
c. project charter - correct answer ✔✔b. project proposal
Major project outcomes and deliverables, how the project will be completed, and a high-level estimate
of the cost and completion time are included in the project proposal.
When does the project defining phase begin?
a. When an idea for a project is identified by a company
b. When the project charter is drafted
c. When all aspects of the triple constraints are met
d. When management decides to select a project for implementation - correct answer ✔✔a. When an
idea for a project is identified by a company
The defining phase begins when an idea for a project is identified.
True or False:
The project planning phase requires fewer resources than the project defining phase. - correct answer
✔✔False
The planning phase generally requires more resources since people with specific knowledge about the
work will need to provide input to the plan.