TEST 1
ANSWER ALL QUESTIONS IN THIS SECTION
QUESTION 1
General supplies are ordered by unit supply personnel using a Manual
Reservation. After approval by release strategy managers, the next MRP run will
convert the purchasing document to a Stock Transport Order (STO), a ________
series document number sent to the SSA for fulfillment. - ANSWERS-d.
10xxxxxxxxxx
QUESTION 2
You want to designate a storage bin for a material in your Provisions SLoc. How
often must this be done for a material number? - ANSWERS-d. ONCE
QUESTION 3
When the MRP process runs, what kind of document will the system create when
the demand quantity is greater than the on-hand quantity for the same material in
the Provisions SLoc? - ANSWERS-b. PR
END OF
PAGE 1
, GCSS ARMY UNIT SUPPLY 2024
TEST 1
QUESTION 4
Performing a PGR for an expendable or durable item will ________ - ANSWERS-
c. Increase the Provisions SLoc
QUESTION 5
A material is found on installation and does not have a corresponding STO/PO.
How will you bring the material onto the Provisional SLoc? - ANSWERS-a.
Transaction code MIGO with movement type 501
QUESTION 6
The Order Status Report (ZPROSTAT) allows you to display which of the
following document types? - ANSWERS-d. All of the above
QUESTION 7
Which of the following component replacements is available for issue to the PB01
work order? - ANSWERS-a. 002277356
END OF