You want to designate a storage bin for a material in your Provisions SLoc. How
often must this be done for a material number? - ANSWER d. ONCE
When the MRP process runs, what kind of document will the system create when the
demand quantity is greater than the on-hand quantity for the same material in the
Provisions SLoc? - ANSWER b. PR
Performing a PGR for an expendable or durable item will ________ - ANSWER c.
Increase the Provisions SLoc
A material is found on installation and does not have a corresponding STO/PO. How
will you bring the material onto the Provisional SLoc? - ANSWER a. Transaction code
MIGO with movement type 501
The Order Status Report (ZPROSTAT) allows you to display which of the following
document types? - ANSWER d. All of the above
Which of the following component replacements is available for issue to the PB01
work order? - ANSWER a. 002277356
. The three-digit Supply Type Unit Code business-area identifier assigned to a
DoDAAC/FEs Unit Supply - ANSWER d. 950
You are using transaction code MD04 to view the effects of Material Requirements
Planning (MRP). How much stock is available for issue in the below image -
ANSWER a. 0
The available quantities in the MD04 report are according to which unit of measure?
- ANSWER a. Ordering
A "start transaction" is set to be the system's first screen displayed once you log in to
GCSS-Army. Setting up a start transaction is ________ - ANSWER c. Performed on a
daily basis
Core GCSS-Army transaction for Unit Supply are accessed from which of the
following transaction codes? - ANSWER b. ZUSMENU