1. The method of computation of Contractor's overhead and profits for Change Order
prices, where both additions and deletions are involved, is found in the:
a) Agreement.
b) Conditions of the Contract.
c) Division 01.
d) Instructions to Bidders. - ANSWER-b) Conditions of the Contract.

2. General Requirements are part of:
a) Supplementary Conditions.
b) Bidding Requirements.
c) Specifications.
d) Summary of Work. - ANSWER-c) Specifications.

3. The three essential considerations in the evaluation of a product are:
a) Requirements, Criteria, and Tests.
b) Costs, Maintenance, and Installation.
c) Life Cycle Cost, Installation Cost, and Maintenance Cost.
d) Case studies, Failures, and Problems. - ANSWER-a) Requirements, Criteria, and
Tests.

4. Whose responsibility is it to furnish the Shop Drawings?
a) The Architect/Engineer
b) The Contractor
c) The Owner
d) The Subcontractor - ANSWER-b) The Contractor

5. The division of the Work among multiple prime Contracts is described in:
a) Instructions to Bidders.
b) Supplementary Conditions.
c) Division 01.
d) Special Conditions. - ANSWER-c) Division 01.

6. During the Project Conception Stage, the A/E may be retained to:
a) Develop outline specifications
b) Describe the character of the mechanical system
c) Prepare renderings
d) Assist in financial feasibility studies - ANSWER-d) Assist in financial feasibility studies

7. What is the main purpose of MasterFormat?
a) for scheduling, value management, recording of design data and managing costs.
b) used during the planning stage of a project.
c) to organize the Project Manual, reference keynotes and detailed cost estimates.

,d) when there is a standardized need for information to appear upon each page of a
project manual. - ANSWER-c) to organize the Project Manual, reference keynotes and
detailed cost estimates.

8. The person who becomes secondarily liable for another's debt or performance is
called the:
a) Guarantee
b) Warrantor
c) Guarantor
d) Warrantee - ANSWER-c) Guarantor

9. Integrated projects are distinguished by all of the following characteristics except:
a) Development of virtual project model through input from a collaborative team
b) Trust-based collaboration between project team members
c) Maximized efficiency through design, fabrication, and construction
d) "Just as needed" team involvement to reduce owner's pre-construction expenses -
ANSWER-d) "Just as needed" team involvement to reduce owner's pre-construction
expenses

10. Outline Specifications are written for
a) only Divisions 02-14 where actual products are discussed
b) Divisions 01-49
c) only Divisions 01-14 (excluding mechanical and electrical)
d) the exclusive use of the A/E - ANSWER-b) Divisions 01-49

11. An example of a MasterFormat Level 3 specification Section is:
a) 05 00 00 Metals.
b) 05 20 00 Metal Joists.
c) 05 21 00 Steel Joist Framing.
d) 05 21 19 Open Web Steel Joist Framing. - ANSWER-d) 05 21 19 Open Web Steel
Joist Framing.

12. What activities take place in the Project Conception Stage?
a) The engineers develop the mechanical and electrical systems.
b) The site is selected and the demolition is done.
c) Feasibility studies and budget is set.
d) The program is evaluated and the engineers are selected. - ANSWER-c) Feasibility
studies and budget is set.

13. The document recommended to organize preliminary construction information into a
standard order on the basis of systems and assemblies is:
a) MasterFormat
b) Uniformat
c) Outline Specifications
d) Project Manual - ANSWER-b) Uniformat

, 14. All design and construction drawings can be classified as one of two types of views:
a) Numeric and graphic.
b) Vertical and horizontal.
c) Scaled and nonscaled.
d) Exterior and interior. - ANSWER-c) Scaled and nonscaled.

15. Substitution requirements and procedures during bidding
a) Are not allowed under most public bidding statutes.
b) Are modified by the Supplementary Conditions.
c) Are stated in the Instructions to Bidders.
d) Are provided by requests by telephone. - ANSWER-c) Are stated in the Instructions
to Bidders.

16. Submittal requirements for Mechanical and Electrical work are specified in:
a) General Conditions
b) Supplementary Conditions
c) Division 01
d) Division 22 and 26 - ANSWER-c) Division 01

17. The Procurement Requirements are
a) a part of the Procurement Documents, but not the Contract Documents.
b) a part of the Contract Documents.
c) a part of the Procurement Documents but not the Project Manual.
d) in the same part as the Contract Modifications. - ANSWER-a) a part of the
Procurement Documents, but not the Contract Documents.

18. Since he or she is most familiar with a product, the manufacturer's representative
should:
a) Write the specification section.
b) Review the specification section.
c) Supply accurate information to the A/E
d) Not be consulted in order to avoid a conflict of interest. - ANSWER-c) Supply
accurate information to the A/E

19. Which of the following requires a Change Order?
a) Extension of bid date.
b) Modification of the Work.
c) Revision of Bidding Documents affecting construction cost.
d) Revision of Bidding Documents affecting completion time. - ANSWER-b) Modification
of the Work.

20. Experienced owners may require project teams to utilize integrated project delivery
based upon:
a) Increased coordination of construction documentation.
b) Desire Greater prefabrication opportunities.
c) Optimized site utilization.

Written for

Institution
Cdt
Course
Cdt

Document information

Uploaded on
November 24, 2024
Number of pages
16
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$12.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF


Also available in package deal

Thumbnail
Package deal
CDT Exams Package Deal Full Solutions Pack
-
7 2024
$ 90.83 More info

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
LUCKYSTAR2022 West Virginia University
View profile
Follow You need to be logged in order to follow users or courses
Sold
912
Member since
4 year
Number of followers
724
Documents
9628
Last sold
2 days ago
LUCKYSTAR2022

Hi there well come to luckystar2022. Here you will find guaranteed quality solution for Nursing and any other Accademic related notes, exams, study guides, cases and many more. 100% value for your time and money. GOOD LUCK

3.5

156 reviews

5
62
4
26
3
25
2
8
1
35

Trending documents

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions