| New Update 2025
A contractor does not notify a change of address and so does not receive a timely
Notice of Renewal. Who is responsible when the contractor does not renew his
license on time? - ANSWER The licensee Contractor
A designated employee should be? - ANSWER at least 18 years old, full time
employee, has passed required examination.
What is the initial Recovery Fund fee? - ANSWER $25
If a contractor earns more than $______ per year, then the contractor requires a
Class A license. - ANSWER $750,000
If a contractor awards more than $______ per payment, the contractor requires a
Class A license. - ANSWER $120,000
An erosion control conservation plan needs to be approved within _____ days. -
ANSWER 45 days.
Where do you go to file an appeal of a violation to the USBC provisions? -
ANSWER to the BBCA
A contractor is required to submit a renewal within ___ days of the expiration
date? - ANSWER 30
, Who can file a complaint against a contractor? - ANSWER any person
What is required when changing the form of entity from a sole proprietorship to
corporation? - ANSWER a new license
What is the maximum fund allowed for a single contractor (per biennium)? -
ANSWER $40,000
To whom should a stop work order be given? - ANSWER owner, owner's agent
or the person doing the work
Within how many days should be submitted an appeal for construction? -
ANSWER 90 days
An appeal of the local building official's decision to refuse to grant a modification
to the USBC MUST be made to the local BBCA within a MAX of how many days? -
ANSWER 90 days
Documents related to a contract should be kept for _____ years. - ANSWER 5
Where should one set of all approved building documents be kept? - ANSWER
at the building site
An erosion control conservation specification needs to be approved within _____
days. - ANSWER 60 days