Problem 18-10
On March 1, 2017, Windsor Construction Company contracted to construct a factory building for Fabrik
Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31,
2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated
billings to Fabrik for 2017, 2018, and 2019 are given below:
2017
2018
2019
Contract costs incurred during the year $2,726,200 $2,566,300 $1,957,500
Estimated costs to complete the contract at 12/31 3,613,800 1,957,500 -0-
Billings to Fabrik during the year 3,180,000 3,490,000 1,670,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be
recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore
income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)
2017
Entry field with correct a - Answers
Problem 18-10 - Answers
On March 1, 2017, Windsor Construction Company contracted to construct a factory building for Fabrik
Manufacturing Inc. for a total contract price of $8,340,000. The building was completed by October 31,
2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated
billings to Fabrik for 2017, 2018, and 2019 are given below: - Answers
- Answers 2017 2018 2019