ICC / UST EXAM QUESTIONS AND ANSWERS
spill prevention equipment consists of a spill bucket that is intended for.... - Answers-
Catching product when transfer hose is detached.
Which statement regarding manual inventory reconciliation is true..... - Answers- it is no
longer an approved method of non-visual monitoring of existing UST systems.
An approved method of leak detection for an underground pressurized piping system
includes... - Answers- A device that automatically restricts product flow through piping.
Under Dispenser Containment was required for all UST systems by - Answers-
12/31/2003
Tanks without secondary containment located within______of a public drinking water
well require recurrent enhanced leak detection testing - Answers- 1,000 Feet
The term Ullage means - Answers- The space or volume above the level of motor
vehicle fuel in a tank or tank system
During a monitor system certification all of the following must be inspected except -
Answers- Fire extinguisher location
When an electrically conductive object is grounded, the electric potential is - Answers-
zero
A_____is installed on the vent riser to prevent vapors from escaping or entering the
system, unless a pressure or vacuum condition exists that exceeds that design opening
pressure or vacuum limit of the cap - Answers- P/V Cap
According to the health and safety code, Tanks installed after July 1, 2003 require a one
time test at installation to determine that the tank is product tight. acceptable methods
are - Answers- inert gas pressure test
Spell containment devices must be attested no less than ________ To demonstrate that
it is capable Of containing the hazardous substance until it is detected in cleaned-up -
Answers- Annually
Spill containment structure or spill bucket is required at the - Answers- fill
Given a monitoring system certification is being conducted on a ust System with double-
wall tank and single walled pressurized piping a positive shut off device is used for
overfill protection to complete the monitoring system certification the service technician
must functionally test all of the following components except the - Answers- Automatic
tank gauge
, All of the following must be included VST monitor system certification except the -
Answers- fuctionality of flapper were ball
According to the ccr title 23 UST regulations a monitoring equipment certification must
be documented using a - Answers- Monitoring system certification form
Emergency shutoff valve or shear valves Shall be installed at what location - Answers-
At-grade level of dispenser device
Spell containers may be constructed of metal - Answers- Exterior wall is protected from
Galvanic corrosion
If no manufacturer training is available a service technician can service the leak
detection can only when - Answers- Approved by the local agency
Tanks without secondary containment located within a specific distance of a public
drinking water Well require enhanced leak detection testing - Answers- Every three
years
All of the following licenses allow An individual to perform a secondary containment
Testing except - Answers- C10 electrical contractor
By December 22nd 1998 all automatic line leak detectors installed on single walled
pressurized piping must be capable of - Answers- Restricting product flow
When removing a liquid from containment areas and the liquid contains fuel you should
- Answers- Handle it as hazardous waste
According to ccr title 23UST regulations a spell container must have a minimum
capacity of what gallons - Answers- Five gallons
According to CCR title 23UST regulations what is the frequency the monitor certification
must be performed - Answers- Every 12 months or annually
Visual monitoring is utilized as the means of release detection or a single wall tank be
conducted on a what basis - Answers- Daily
Purpose of spill and overfill protection equipment is to minimize the potential for a
release during - Answers- fuel deliveries
Which of the following is a potential Symptom of toxic petroleum exposure - Answers-
Dizziness
Tremors
eye irritation
All the above
spill prevention equipment consists of a spill bucket that is intended for.... - Answers-
Catching product when transfer hose is detached.
Which statement regarding manual inventory reconciliation is true..... - Answers- it is no
longer an approved method of non-visual monitoring of existing UST systems.
An approved method of leak detection for an underground pressurized piping system
includes... - Answers- A device that automatically restricts product flow through piping.
Under Dispenser Containment was required for all UST systems by - Answers-
12/31/2003
Tanks without secondary containment located within______of a public drinking water
well require recurrent enhanced leak detection testing - Answers- 1,000 Feet
The term Ullage means - Answers- The space or volume above the level of motor
vehicle fuel in a tank or tank system
During a monitor system certification all of the following must be inspected except -
Answers- Fire extinguisher location
When an electrically conductive object is grounded, the electric potential is - Answers-
zero
A_____is installed on the vent riser to prevent vapors from escaping or entering the
system, unless a pressure or vacuum condition exists that exceeds that design opening
pressure or vacuum limit of the cap - Answers- P/V Cap
According to the health and safety code, Tanks installed after July 1, 2003 require a one
time test at installation to determine that the tank is product tight. acceptable methods
are - Answers- inert gas pressure test
Spell containment devices must be attested no less than ________ To demonstrate that
it is capable Of containing the hazardous substance until it is detected in cleaned-up -
Answers- Annually
Spill containment structure or spill bucket is required at the - Answers- fill
Given a monitoring system certification is being conducted on a ust System with double-
wall tank and single walled pressurized piping a positive shut off device is used for
overfill protection to complete the monitoring system certification the service technician
must functionally test all of the following components except the - Answers- Automatic
tank gauge
, All of the following must be included VST monitor system certification except the -
Answers- fuctionality of flapper were ball
According to the ccr title 23 UST regulations a monitoring equipment certification must
be documented using a - Answers- Monitoring system certification form
Emergency shutoff valve or shear valves Shall be installed at what location - Answers-
At-grade level of dispenser device
Spell containers may be constructed of metal - Answers- Exterior wall is protected from
Galvanic corrosion
If no manufacturer training is available a service technician can service the leak
detection can only when - Answers- Approved by the local agency
Tanks without secondary containment located within a specific distance of a public
drinking water Well require enhanced leak detection testing - Answers- Every three
years
All of the following licenses allow An individual to perform a secondary containment
Testing except - Answers- C10 electrical contractor
By December 22nd 1998 all automatic line leak detectors installed on single walled
pressurized piping must be capable of - Answers- Restricting product flow
When removing a liquid from containment areas and the liquid contains fuel you should
- Answers- Handle it as hazardous waste
According to ccr title 23UST regulations a spell container must have a minimum
capacity of what gallons - Answers- Five gallons
According to CCR title 23UST regulations what is the frequency the monitor certification
must be performed - Answers- Every 12 months or annually
Visual monitoring is utilized as the means of release detection or a single wall tank be
conducted on a what basis - Answers- Daily
Purpose of spill and overfill protection equipment is to minimize the potential for a
release during - Answers- fuel deliveries
Which of the following is a potential Symptom of toxic petroleum exposure - Answers-
Dizziness
Tremors
eye irritation