When tower crane is erected/dismantled, written instructions must be - CORRECT ANSWER-On site Tower crane erection/dismantling shall be performed under direct supervision of the - CORRECT ANSWER-Designated person What is the minimum clearance from obstruction when the tower crane freely rotates 360•? - CORRECT ANSWER-6 ft 6 in What must the crane operator do when a load is suspended - CORRECT ANSWER-Remain at the controls How often should the hoist rope be lubricated? - CORRECT ANSWER-Every 200 hours If block is twisted, it may be necessary to fix the ______________ and make a few empty runs with the hook and trolley and then reopen - CORRECT ANSWER-Twist compensator How many wraps shall be on the drum when the block is at its lowest point - CORRECT ANSWER-3 The radius on a crane chart refers to - CORRECT ANSWER-Center of rotation to center of gravity of load or hook What would cal for a running rope to be taken out of service - CORRECT ANSWER-12 randomly distributed broken wires in one lay or 4 in one strand in one lay maintainence personnel are only permitted to operate crane when - CORRECT ANSWER-Only when performing the maintenance duties

Show more Read less
Institution
NCCCO Tower
Course
NCCCO tower









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NCCCO tower
Course
NCCCO tower

Document information

Uploaded on
October 12, 2024
Number of pages
8
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

NCCCO tower exam 7.2020 Questions
with Actual Answers Graded A+

When tower crane is erected/dismantled, written instructions must be - CORRECT
ANSWER-On site



Tower crane erection/dismantling shall be performed under direct supervision of the -
CORRECT ANSWER-Designated person



What is the minimum clearance from obstruction when the tower crane freely rotates
360•? - CORRECT ANSWER-6 ft 6 in



What must the crane operator do when a load is suspended - CORRECT ANSWER-
Remain at the controls



How often should the hoist rope be lubricated? - CORRECT ANSWER-Every 200 hours



If block is twisted, it may be necessary to fix the ______________ and make a few
empty runs with the hook and trolley and then reopen - CORRECT ANSWER-Twist
compensator



How many wraps shall be on the drum when the block is at its lowest point - CORRECT
ANSWER-3



The radius on a crane chart refers to - CORRECT ANSWER-Center of rotation to center
of gravity of load or hook



What would cal for a running rope to be taken out of service - CORRECT ANSWER-12
randomly distributed broken wires in one lay or 4 in one strand in one lay



maintainence personnel are only permitted to operate crane when - CORRECT
ANSWER-Only when performing the maintenance duties

, Crane must be a minimum of ____ away from power lines up to 50kV - CORRECT
ANSWER-10ft



How do you determine the size or the mats/blocking needed under tower crane
outriggers? - CORRECT ANSWER-Ground bearing capacity of The supporting surface



A crane should always be barricaded within - CORRECT ANSWER-The outermost
swing radius of the rear of the superstructure ( counterweight)



The crane must have a _________ inspection performed both monthly and yearly. This
information must be documented by the employer that conducts the inspection. -
CORRECT ANSWER-Periodic



What is the weight of steel per cubic foot ? - CORRECT ANSWER-490 lbs



If radius is in between On load chart, you should use - CORRECT ANSWER-Next
longer radius



If the boom angle is in between On The load chart , you should - CORRECT ANSWER-
Use next lower boom angle



Wind blowing on the job site can cause: - CORRECT ANSWER-Increase radius and
lower tower crane capacity



In most cases tower crane operations should be shut down with winds in excess of -
CORRECT ANSWER-45 mph



What is the weight of steel ? - CORRECT ANSWER-490 pounds per cubic foot



On a self - erecting tower crane , which of the following is included in the set up ? -
CORRECT ANSWER-Preparing foundation or ground compaction
$10.69
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Vaster
5.0
(2)

Also available in package deal

Thumbnail
Package deal
NCCCO EXAM BUNDLE QUESTIONS WITH 100% COMPLETE SOLUTIONS
-
25 2024
$ 271.45 More info

Get to know the seller

Seller avatar
Vaster Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
4
Member since
1 year
Number of followers
1
Documents
794
Last sold
1 month ago

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions