Question 1:
Which of the following is the first step in analyzing site readiness prior to a Pure
FlashArray installation?
A) Installing the FlashArray hardware
B) Conducting a site survey to assess environmental conditions
C) Configuring the network switches
D) Training the staff on FlashArray operations
Answer: B) Conducting a site survey to assess environmental conditions
Explanation: The first step involves evaluating the site's environmental conditions, such as
power, cooling, space, and network infrastructure, to ensure they meet the requirements for
FlashArray installation.
Question 2:
When assessing power requirements for a Pure FlashArray installation, which of the
following should be considered?
A) The color of the server racks
B) The number of users accessing the system
C) The total power consumption of the FlashArray and redundancy options
D) The type of operating system used
Answer: C) The total power consumption of the FlashArray and redundancy options
Explanation: It's essential to determine the FlashArray's power needs and ensure that the
site's power infrastructure can support it, including redundancy for high availability.
Question 3:
Which network requirement is critical for the installation of a Pure FlashArray?
A) Presence of a wireless network
B) Sufficient LAN bandwidth and appropriate network segmentation
C) Use of IPv6 addressing
D) Having a VPN setup
Answer: B) Sufficient LAN bandwidth and appropriate network segmentation
Explanation: Adequate LAN bandwidth and proper network segmentation are crucial to
handle data traffic efficiently and maintain security.
Question 4:
Prior to installation, verifying the availability of which of the following is essential for
remote management of the FlashArray?
A) Physical access to the data center
B) Remote Assist tool compatibility
C) Telephone lines for voice calls
D) Satellite internet connection
1
, Pure Certified FlashArray Implementation Specialist
Answer: B) Remote Assist tool compatibility
Explanation: Ensuring that Remote Assist tools are compatible and available is vital for
effective remote management and troubleshooting.
Question 5:
Which of the following environmental factors should be assessed during site readiness
evaluation for FlashArray installation?
A) Humidity levels and cooling capacity
B) Office layout and furniture
C) Employee work hours
D) Brand of electrical outlets
Answer: A) Humidity levels and cooling capacity
Explanation: Proper environmental conditions like humidity and cooling are essential to
maintain optimal operating temperatures for the FlashArray.
Question 6:
What is the importance of checking the physical space availability before installing a
Pure FlashArray?
A) To ensure there is enough space for future expansions
B) To verify the aesthetic appeal of the data center
C) To confirm there is sufficient space for the FlashArray units and proper airflow
D) To arrange for enough seating for the installation team
Answer: C) To confirm there is sufficient space for the FlashArray units and proper airflow
Explanation: Adequate space ensures that the FlashArray fits well and that there is enough
airflow for cooling and maintenance.
Question 7:
Which documentation is vital to collect during site readiness analysis?
A) Employee personal information
B) Existing network diagrams and infrastructure documentation
C) Software license agreements
D) Marketing materials of the site
Answer: B) Existing network diagrams and infrastructure documentation
Explanation: Understanding the current network setup helps in planning the integration of
the FlashArray effectively.
Question 8:
Why is it important to assess the redundancy of power sources during site readiness for
FlashArray installation?
2
, Pure Certified FlashArray Implementation Specialist
A) To reduce the cost of installation
B) To ensure uninterrupted operation in case of power failures
C) To make the setup more portable
D) To comply with software licensing terms
Answer: B) To ensure uninterrupted operation in case of power failures
Explanation: Power redundancy ensures that the FlashArray remains operational even
during power outages, maintaining data availability.
Question 9:
Which of the following is a key consideration when evaluating network security for
FlashArray installation?
A) The color of network cables
B) The use of network segmentation and access controls
C) The brand of routers used
D) The type of Ethernet connectors
Answer: B) The use of network segmentation and access controls
Explanation: Implementing network segmentation and access controls protects the
FlashArray from unauthorized access and potential threats.
Question 10:
When planning the site readiness, which compliance requirement might need to be
considered for FlashArray installation?
A) The company logo placement
B) Data protection regulations such as GDPR or HIPAA
C) The office dress code
D) The number of employees in the company
Answer: B) Data protection regulations such as GDPR or HIPAA
Explanation: Compliance with data protection laws ensures that the FlashArray installation
meets legal standards for data security and privacy.
Section II: Validate the Implementation Workbook Data
Question 11:
What is the primary purpose of the Implementation Workbook in a FlashArray
deployment?
A) To serve as a user manual for end-users
B) To document the configuration and deployment details for validation
C) To provide marketing information about FlashArray
D) To list all available software updates
3
, Pure Certified FlashArray Implementation Specialist
Answer: B) To document the configuration and deployment details for validation
Explanation: The Implementation Workbook records all configuration settings and
deployment steps, which are essential for validating that the installation meets the required
specifications.
Question 12:
Which of the following data should be validated in the Implementation Workbook
before proceeding with the installation?
A) Employee contact information
B) Network configurations and IP addresses
C) The physical layout of the office
D) The version of office productivity software
Answer: B) Network configurations and IP addresses
Explanation: Ensuring that network settings are correctly documented prevents connectivity
issues post-installation.
Question 13:
When validating the Implementation Workbook, why is it important to check the
storage capacity requirements?
A) To determine the color of the FlashArray units
B) To ensure that the FlashArray has sufficient capacity to meet the organization's data needs
C) To decide on the type of backup software to use
D) To calculate the number of employees required for maintenance
Answer: B) To ensure that the FlashArray has sufficient capacity to meet the organization's
data needs
Explanation: Validating storage capacity ensures that the system can handle current and
future data growth without performance degradation.
Question 14:
Which configuration aspect should be cross-verified in the Implementation Workbook
to ensure proper data redundancy?
A) User access levels
B) RAID configurations and replication settings
C) The brand of network cables
D) The operating system version
Answer: B) RAID configurations and replication settings
Explanation: RAID and replication settings are critical for data redundancy, protecting
against data loss in case of hardware failures.
4