and Answers Guaranteed Pass.
All of the following must follow OSHA standards except ___
A-religious establishments
B-general contractor with one employee
C-landscape contractors
D-equipment rental business - Answer A-religious establishemnts
The minimum number of employees that will require a contractor to obtain workers compensation
insurance is ____ employees
A- one
B- three
C- four
D- Ten - Answer A - one
The type of Bond That guarantees that the contractor will preform the work in accordance with the
contract is known as a ___ bond
A-bid
B-payment
C-performance
D-stipulated - Answer C- performance
A short-term project schedule is a detailed explanation of the next two weeks of construction activities
and should be developed and/or reviewed by all of the following except ___
, A-superintendent
B-architect
C-subcontractors
D-project engineer - Answer B- architect
The ___ usually prepared the project schedule
A-architect
B-owner
C-project Manager
D-engineer - Answer C- project manger
In order to provide adequate control, the project schedule should be formally reviews and updated
A-at the project commencement
B-at least once every 30 days
C- at least once every 6 months
D- at the project closeout - Answer B-Atleast every 30 days
A contract will not be enforced if it is
A- oral
B- illegal
C- no work is accomplished for 90 days
D- all of the above - Answer B- illegal
According to the statue of frauds, a contract need not be in writing and still be enforceable in Florida if
less than ___ and ___