The CO is a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. True What part of teh FAR prescribes policies and procedures for assigning and perofrming contract administration and contract audit services? 42 The CO may delegate additional functions to the CAO beyond those listed in FAR 42.302 False In a postaward meeting, the CO will conduct a preliminary meeting of government personnel and will designate or act as teh chairperson at the conference. True or Fals1 True What should the contract management plan include, other than being as simple and precise as possible? What must me done. When it must take place. Who must do it. How it is to be accomplished. Where it is to be accomplished. True or False: The COR plays an important role in the postaward phase of the acquisition and is the eyes and ears of the contracting officer. True True or False: The DD Form 1484A may be used in conducting the conference and in preparing the conference report. True True or False: All invoice payments, with the exception of interim payments on cost reimbursement contracts for services, must be supported by a receiving report or other goverment documentation authorizing payment. True The government will not make invoice payment earlier than 7 days prior to the due dates specified in the contract unless what is determined by the agency head? To make earlier payment on a case-by-case basis. That the use of accelerated payment methods are necessary. What are some examples of contract financing methods? Progress payment. Loan Guarantees. Performance base payments. Advanced payments. Partial Delivery Payments. Contracting Officers can only provide property to contractors when what is clearly demonstrated? It is in the government's best interest. Overal benefit significantly outweighs the increased cost of admin. Does not substantially increase the gov'ts assumption of risk. Goverment requirments cannot otherwise be met. True or False: Government property shall normall be provided on a rent-free basis in performance of the contract under which it is accountable or otherwise authorized. True True or Fall: Contractors are held liable for loss of government property. False True or False: The rate cycle process all starts when the contractor submits a forward pricing rate proposal (FPRP) at the beginning of an accounting period. DCAA and DCMA taket hat proposal through a rpocess that will ultimately lead to a Forward Processing Rate Agreement (FPRA) True True or False: Billing rates are used to adjust and close out contracts False: Billing rates provide a mother for interim reimbursement of indirect costs at estimated rates. What is true about billing rates as an indirect cost rate? They are established temporarily for interim reimbursement of incurred indirect costs. They are adjusted as necessary pedning establishment of final indirect cost rates. Are indirect costs the same as final rates? No Final indrect cost rates are established on what basis? Contracting officer determination procedure and auditor dermination procedure Who is involved in performance managment? Customer. Stakeholders. Contractor. True or False: A stakeholder is anyone with an interest in teh acquisition and its outcome. True True or False: Governance are individuals or organizations that must approve the requirement and acquisition strategies and may be in the contracting organization or requiring activity. True True or False: A good understanding of the "as is state" or baseline (including current, past, and forecacasted requirements, processes, performance, and spending) can help the acquisition team mroe effectively develop plans and actions that will improve performance of the new requirement and implementation strategy. True

Show more Read less
Institution
CON 3900
Course
CON 3900









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CON 3900
Course
CON 3900

Document information

Uploaded on
September 14, 2024
Number of pages
7
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CON 3900 Administer Contracts
test questions and answers
The CO is a person with the authority to enter into, administer,
and/or terminate contracts and make related determinations and
findings.
True
What part of teh FAR prescribes policies and procedures for
assigning and perofrming contract administration and contract audit
services?
42
Previous
Play
Next
Rewind 10 seconds
Move forward 10 seconds
Unmute
0:01
/
0:15
Full screen
Brainpower
Read More
The CO may delegate additional functions to the CAO beyond those
listed in FAR 42.302
False
In a postaward meeting, the CO will conduct a preliminary meeting
of government personnel and will designate or act as teh
chairperson at the conference. True or Fals1

, True
What should the contract management plan include, other than
being as simple and precise as possible?
What must me done. When it must take place. Who must do it. How
it is to be accomplished. Where it is to be accomplished.
True or False: The COR plays an important role in the postaward
phase of the acquisition and is the eyes and ears of the contracting
officer.
True
True or False: The DD Form 1484A may be used in conducting the
conference and in preparing the conference report.
True
True or False: All invoice payments, with the exception of interim
payments on cost reimbursement contracts for services, must be
supported by a receiving report or other goverment documentation
authorizing payment.
True
The government will not make invoice payment earlier than 7 days
prior to the due dates specified in the contract unless what is
determined by the agency head?
To make earlier payment on a case-by-case basis. That the use of
accelerated payment methods are necessary.
What are some examples of contract financing methods?
Progress payment. Loan Guarantees. Performance base payments.
Advanced payments. Partial Delivery Payments.
Contracting Officers can only provide property to contractors when
what is clearly demonstrated?
It is in the government's best interest. Overal benefit significantly
outweighs the increased cost of admin. Does not substantially
increase the gov'ts assumption of risk. Goverment requirments
cannot otherwise be met.
True or False: Government property shall normall be provided on a
rent-free basis in performance of the contract under which it is
accountable or otherwise authorized.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BRAINBOOSTERS Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
654
Member since
2 year
Number of followers
250
Documents
22617
Last sold
2 days ago

In this page you will find all documents , flashcards and package deals offered by seller BRAINBOOSTERS

4.5

339 reviews

5
264
4
30
3
21
2
5
1
19

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions