Select the Better Buying Power initiative that should be implemented to address the problem. - Implement "should cost" based management Assign each task to the individual responsible for its completion. a) Life Cycle Logistician b) Program Manager - a) Develop and implement risk planning; Identify risks that impact multiple Integrated Product Teams and coordinate risk management efforts; Revisit identified risks to verify risk analysis results. b) Assign responsibility and authority for risk management activities; Chair the Risk Management Board; Allocate resources to manage risks 4) Match the responsibilities of the life cycle logistician with the appropriate task. a) Manage Product Support Arrangements b) Integrate Support Strategies c) Employ Diagnostics and Prognostics d) Apply Supply Chain Management - a) Create contract, determine if the contract must be open to competition, and indicate the renegotiation period b) Discourage designs that include hazardous materials that require special handling c) Request further testing in response to results d) Develop retail supply buffers to ensure adequate parts are available Apply Supply Chain Management - Ensure that sufficient inventories are maintained at the depot and field levels Negotiate a contract to ensure a continuous inventoryAs a Devon analyzes a risk, what is the most appropriate sequence of her actions? - Quantify the cost impacts, compare impacts with the affordability cap, and set reminder to review potential cost impact in 3 months As Devon has been reviewing several responses to RFPs from contractors, she's noticed some vague indirects costs that over the course of the contract will add ten percent to the over all cost. As Devon is identifying risk within a program, what are some methods that she might use? Select all that apply. - -Talking with experts and leads about likely risks -Researching independent assessments and trade studies -Reviewing similar programs As Devon works to manage risk what are her responsibilities as a Life Cycle Logistician, in contrast to the Program Manager? Select all that apply. - -Assist in reporting risk status to senior management personnel, revisit identified risks to verify risk analysis results, and support engineering trade-off analyses to ensure risk elements are considered. -Develop and implement the risk planning outlined in documentation, conduct risk analysis to provide to decision makers, and recommend risk mitigation options, estimate funding requirements, support implementation, and track progress of efforts, and identify risks that impact multiple Integrated Product Teams and coordinate risk management efforts Assign each task to the individual responsible for its completion. a) Life Cycle Logistician b) Program Manager - a) Develop and implement risk planning; Identify risks that impact multiple Integrated Product Teams and coordinate risk management efforts; Revisit identified risks to verify risk analysis results. b) Assign responsibility and authority for risk management activities; Chair the Risk Management Board; Allocate resources to manage risksChoose the correct definition of life cycle product support. - The package of the support functions required to deploy and maintain the capability of major weapon systems, including all functions related to weapon system readiness. Choose the ways a life cycle logistician might interact with an Independent Logistics Assessment team. (Select all that apply.) -Provide data and documentation to the Independent Logistics Assessment team from a project that the life cycle logistician has been not working on -Participate as an Independent Logistics Assessment member on a project that the life cycle logistician has been working on -Provide data and documentation to the Independent Logistics Assessment team from a project that the life cycle logistician has been working on -Participate as an Independent Logistics Assessment member on a project that the life cycle logistician has not been working on - -Provide data and documentation to the Independent Logistics Assessment team from a project that the life cycle logistician has been working on -Participate as an Independent Logistics Assessment member on a project that the life cycle logistician has not been working on Devon experienced a problematic situation as she's worked on her project. After Milestone A, the system that Devon has been working on has been given the go-ahead to progress through the acquisition process despite the fact that she's identified some potential problems with deploying it in selected environments. Select the Better Buying Power initiatives that should be implemented to address the problem. - Use the Technology Development phase for true risk reduction Devon has been assigned to a program that has clear ties to one contractor. Several times decisions have been made that accommodate the contractor's ability to deliver rather than the requirements outlined in the Capabilities Design Document. Select the Better Buying Power initiative that should be implemented to address the problem. - Increase use of Performance Based LogisticsDevon has noticed that some of the proposed requirements are resulting in outsized Life Cycle Cost Estimates. She and the logistics team have expressed their concerns to the Integrated Product Team, but it still seems to be a problem. Select the Better Buying Power initiatives that should be implemented to address the problem. - Build stronger partnerships with the requirements community to control costs During testing, one part is failing every 15 hours of usage. - Reliability

Show more Read less
Institution
LOG 100 - Life Cycle Logistics Fundamentals (Modul
Course
LOG 100 - Life Cycle Logistics Fundamentals (Modul









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
LOG 100 - Life Cycle Logistics Fundamentals (Modul
Course
LOG 100 - Life Cycle Logistics Fundamentals (Modul

Document information

Uploaded on
August 4, 2024
Number of pages
10
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

LOG 100 - Life Cycle Logistics
Fundamentals (Module 5)
Select the Better Buying Power initiative that should be implemented to address the problem. -
Implement "should cost" based management



Assign each task to the individual responsible for its completion.

a) Life Cycle Logistician

b) Program Manager - a) Develop and implement risk planning;

Identify risks that impact multiple Integrated Product Teams and coordinate risk management efforts;
Revisit identified risks to verify risk analysis results.

b) Assign responsibility and authority for risk management activities;

Chair the Risk Management Board;

Allocate resources to manage risks



4) Match the responsibilities of the life cycle logistician with the appropriate task.

a) Manage Product Support Arrangements

b) Integrate Support Strategies

c) Employ Diagnostics and Prognostics

d) Apply Supply Chain Management - a) Create contract, determine if the contract must be open
to competition, and indicate the renegotiation period

b) Discourage designs that include hazardous materials that require special handling

c) Request further testing in response to results

d) Develop retail supply buffers to ensure adequate parts are available



Apply Supply Chain Management - Ensure that sufficient inventories are maintained at the depot
and field levels

Negotiate a contract to ensure a continuous inventory

, As a Devon analyzes a risk, what is the most appropriate sequence of her actions? - Quantify the
cost impacts, compare impacts with the affordability cap, and set reminder to review potential cost
impact in 3 months



As Devon has been reviewing several responses to RFPs from contractors, she's noticed some vague
indirects costs that over the course of the contract will add ten percent to the over all cost.




As Devon is identifying risk within a program, what are some methods that she might use? Select all that
apply. - -Talking with experts and leads about likely risks

-Researching independent assessments and trade studies

-Reviewing similar programs



As Devon works to manage risk what are her responsibilities as a Life Cycle Logistician, in contrast to the
Program Manager? Select all that apply. - -Assist in reporting risk status to senior management
personnel, revisit identified risks to verify risk analysis results, and support engineering trade-off
analyses to ensure risk elements are considered.

-Develop and implement the risk planning outlined in documentation, conduct risk analysis to provide to
decision makers, and recommend risk mitigation options, estimate funding requirements, support
implementation, and track progress of efforts, and identify risks that impact multiple Integrated Product
Teams and coordinate risk management efforts



Assign each task to the individual responsible for its completion.

a) Life Cycle Logistician

b) Program Manager - a) Develop and implement risk planning;

Identify risks that impact multiple Integrated Product Teams and coordinate risk management efforts;
Revisit identified risks to verify risk analysis results.

b) Assign responsibility and authority for risk management activities;

Chair the Risk Management Board;

Allocate resources to manage risks

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PatrickKaylian Delaware State University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1818
Member since
2 year
Number of followers
1043
Documents
22126
Last sold
1 day ago

3.8

316 reviews

5
147
4
60
3
54
2
15
1
40

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions