100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

PJM Sample Test Review 2024 Questions and Answers

Rating
-
Sold
-
Pages
17
Grade
A+
Uploaded on
05-06-2024
Written in
2023/2024

PJM Sample Test Review 2024 Questions and Answers Real time transmission constraints or contingencies may be alleviated with generators operating ______________ - Correct Answer ️️ -off cost out of merit. Monitoring ___________ may give insights into system constraints. - Correct Answer ️️ -Monitoring LMP's PJM calls for _____________ reserves to recover ace so that tie line schedules are maintained. - Correct Answer ️️ -PJM calls on synchronized reserves If not cancelled by PJM, the minimum generation alert expires at the end of the specified ______________. - Correct Answer ️️ -light load period When PJM declares a hot weather alert, the generation dispatcher should determine if maintenance can be deferred and notify all generating stations and key personnel. - Correct Answer ️️ - During system restoration, the two categories of reserves are dynamic and spinning. - Correct Answer ️️ - During system restoration, frequency should be maintained between 59.75 and 61.00 Hertz. - Correct Answer ️️ - PJM issues a heavy load voltage schedule. Member companies who own generation facilities should ensure voltage regulators on generating units are in service & automatic. - Correct Answer ️️ - A unit being dispatched economically by PJM should set its megawatt output based on the unit's dispatch rate or desired megawatt level. - Correct Answer ️️ - A fossil steam unit is considered fuel limited when it is not capable of running at its maximum capacity for the next 72 hours - Correct Answer ️️ - During system restoration prior to synchronization of a unit, the dispatcher should ensure sufficient load is available to stabilize unit operation. - Correct Answer ️️ - A large unit in an external control area near PJM/PJM West trips. The PJM operator will see ace remain the same, frequency decrease. - Correct Answer ️️ - LMPs will change when marginal generator output changes - Correct Answer ️️ - The two control signals sent by the PJM E M S are regulation and dispatch rate (desired MW output). - Correct Answer ️️ - An all-call is the one-way communication system used to disseminate information to market operation centers. - Correct Answer ️️ - Real time bus prices may be monitored using data viewer. - Correct Answer ️️ - Not offering an available PJM capacity resource into the day ahead market is a violation of PJMs two settlement market rules. - Correct Answer ️️ - A unit that fails to start when scheduled, would be classified as an unplanned outage. - Correct Answer ️️ - Maximum Generation Emergency is declared by PJM when generation is required above the highest incremental economic cost. - Correct Answer ️️ - Maintenance outages are permitted when a unit can be held online until the following Monday, and system reliability is not affected - Correct Answer ️️ - If PJM ace shows over-generation, actual imports are less than scheduled. - Correct Answer ️️ - PJM will request a Supplementary Status Report when a Maximum Generation Emergency Alert is issued. - Correct Answer ️️ - If a fossil steam unit has less than 32 hours of fuel at maximum capacity, it should be bid at maximum emergency. - Correct Answer ️️ - The loss of a large generation unit on the PJM system can be detected by monitoring frequency and PJM ace. - Correct Answer ️️ - A 1000 megawatt unit has tripped in the PJM control area and the PJM

Show more Read less
Institution
PJM Generation
Course
PJM Generation










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation
Course
PJM Generation

Document information

Uploaded on
June 5, 2024
Number of pages
17
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PJM Sample Test Review 2024 Questions and Answers Real time transmission constraints or contingencies may be alleviated with generators operating ______________ - Correct Answer ✔️✔️-off cost out of merit. Monitoring ___________ may give insights into system constraints. - Correct Answer ✔️✔️-Monitoring LMP's PJM calls for _____________ reserves to recover ace so that tie line schedules are maintained. - Correct Answer ✔️✔️-PJM calls on synchronized reserves If not cancelled by PJM, the minimum generation alert expires at the end of the specified ______________. - Correct Answer ✔️✔️-light load period When PJM declares a hot weather alert, the generation dispatcher should determine if maintenance can be deferred and notify all generating stations and key personnel. - Correct Answer ✔️✔️- During system restoration, the two categories of reserves are dynamic and spinning. - Correct Answer ✔️✔️- During system restoration, frequency should be maintained between 59.75 and 61.00 Hertz. - Correct Answer ✔️✔️- PJM issues a heavy load voltage schedule. Member companies who own generation facilities should ensure voltage regulators on generating units are in service & automatic. - Correct Answer ✔️✔️- A unit being dispatched economically by PJM should set its megawatt output based on the unit's dispatch rate or desired megawatt level. - Correct Answer ✔️✔️- A fossil steam unit is considered fuel limited whe n it is not capable of running at its maximum capacity for the next 72 hours - Correct Answer ✔️✔️- During system restoration prior to synchronization of a unit, the dispatcher should ensure sufficient load is available to stabilize unit operation. - Corre ct Answer ✔️✔️- A large unit in an external control area near PJM/PJM West trips. The PJM operator will see ace remain the same, frequency decrease. - Correct Answer ✔️✔️- LMPs will change when marginal generator output changes - Correct Answer ✔️✔️- The t wo control signals sent by the PJM E M S are regulation and dispatch rate (desired MW output). - Correct Answer ✔️✔️- An all -call is the one -way communication system used to disseminate information to market operation centers. - Correct Answer ✔️✔️- Real t ime bus prices may be monitored using data viewer. - Correct Answer ✔️✔️- Not offering an available PJM capacity resource into the day ahead market is a violation of PJMs two settlement market rules. - Correct Answer ✔️✔️- A unit that fails to start when scheduled, would be classified as an unplanned outage. - Correct Answer ✔️✔️- Maximum Generation Emergency is declared by PJM when generation is required above the highest incremental economic cost. - Correct Answer ✔️✔️- Maintenance outages are permitted when a unit can be held online until the following Monday, and system reliability is not affected - Correct Answer ✔️✔️- If PJM ace shows over -generation, actual imports are less than scheduled. - Correct Answer ✔️✔️- PJM wi ll request a Supplementary Status Report when a Maximum Generation Emergency Alert is issued. - Correct Answer ✔️✔️- If a fossil steam unit has less than 32 hours of fuel at maximum capacity, it should be bid at maximum emergency. - Correct Answer ✔️✔️- The loss of a large generation unit on the PJM system can be detected by monitoring frequency and PJM ace. - Correct Answer ✔️✔️- A 1000 megawatt unit has tripped in the PJM control area and the PJM ace now indicates under -generation of 1050 Megawatt. PJM sh ould request 100% synchronized reserves be loaded. - Correct Answer ✔️✔️- Alerts are issued in advance of a scheduled load period to allow sufficient time for the generation dispatcher to prepare for the anticipated capacity shortages - Correct Answer ✔️✔️- The amount of synchronized reserves must be large enough to cover the loss of the largest single energy contingency. - Correct Answer ✔️✔️-

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
BrittieDonald Howard Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
397
Member since
2 year
Number of followers
162
Documents
20438
Last sold
14 hours ago
BrittieDonald Study Solutions.

Get Help in Your Due Online and Actual Exams, Assignments with Well Researched and Up-to date Study Materials for Guaranteed Success

3.3

78 reviews

5
31
4
13
3
7
2
5
1
22

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions