100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CAPM Test Bank with 100% Correct Solutions |Latest 2024/2025

Rating
-
Sold
-
Pages
78
Grade
A+
Uploaded on
29-05-2024
Written in
2023/2024

CAPM Test Bank with 100% Correct Solutions. 5 process groups ️ Initiating Planning Executing Monitoring and Controlling Closing Ten knowledge areas ️ Integration Scope Time Cost Quality HR Communications Risk Procurement Stakeholder management total float formula ️ total float = late finish - early finish normal distribution ️ bell curve - symmetrical distribution - 50% chance of falling below the mean and 50% chance of falling above the mean (1sigma=68.27%. 2sigma = 95.45%. 3sigma= 99.73%) triangular distribution ️ when there are 3 possible values w/ equal probability - distribution is a triangle. A= lowest value, B= highest value, M = most likely value beta distribution (PERT) ️ triangular distribution w/ more weight given to the most likely estimate (can be asymmetrical). O = optimistic estimate, ML=most likely estimate, P=pessimistic estimate mean for a beta distribution ️ mean = (O + 4ML + P)/6 standard deviation for beta distribution ️ standard deviation = (P-O)/6 statistical sums ️ project mean is the sum of the means of the individual tasks. project standard deviation is the square root of the project variance earned value management ️ used to monitor the progress of a project and is an analytical technique. uses 3 independent values - PV, AC, EV planned value (PV) ️ the budget or the portion of the approved cost estimate planned to be spent during a given period actual cost (AC) ️ the total of direct and indirect costs incurred in accomplishing work during a given period earned value (EV) ️ the budget for the work accomplished in a given period cost variance (CV) ️ CV = EV - AC schedule variance (SV) ️ SV = EV - PV cost performance index (CPI) ️ CPI = EV/AC schedule performance index (SPI) ️ SPI = EV/PV positive CV indicates, negative CV indicates ️ costs are below budget, costs are overrun positive SV indicates, negative SV indicates ️ a project is ahead of schedule, a project is behind schedule CPI greater than 1.0 indicates ️ costs are below budget SPI greater than 1.0 indicates ️ project is ahead of schedule CPI less than 1.0 indicates ️ costs are over budget SPI less than 1.0 indicates ️ a project is behind schedule estimate at completion (EAC) ️ the amount we expect the total project to cost on completion and as of the "data date" (time now) new estimate technique for finding EAC ️ EAC = AC/new estimate for remaining work new estimate is most applicable when: ️ the actual performance to date shows that the original estimates were fundamentally flawed or when they are no longer accurate because of changes in conditions relating to the project original estimate technique for finding EAC ️ EAC = AC/(BAC - EV) original estimate is most applicable when: ️ actual variances to date are seen as being the exception, and the expectations for the future are that the original estimates are more reliable than the actual work effort efficiency date performance estimate low technique for finding EAC ️ EAC = AC + (BAC - EV)/CPI or EAC = BAC/CPI performance estimate low formula is most applicable when: ️ future variances are projected to approximate the same level as current variances performance estimate high technique for finding EAC ️ EAC = AC + (BAC - EV) / (CPI)(SPI) performance estimate high formula is most applicable when: ️ the project is over budget and the schedule impacts the work remaining to be completed BAC ️ budget at completion. the total budgeted cost of all approved activities ETC ️ estimate to complete - the estimate for completing the remaining work for a scheduled activity ETC when past variances are considered to be atypical ️ ETC = BAC - EV ETC when prior variances are considered to be typical of future variances ️ ETC = (BAC - EV)/CPI communications channels ️ channels = (n(n-1))/2. n - number of ppl rule of seven ️ if 7 or more observations occur in one direction, or a run of 7 observations occurs either above or below the mean, they should be investigated to determine if they have an assignable cause. business value ️ the entire value of a business - the total sum of all tangible and intangible elements colocation ️ project team members are physically located close to one another in order to improve communications, working relations, and productivity constraint ️ a restriction or limitation that may force a certain course of action or inaction enterprise environmental factors ️ external or internal factors that can influence a project's success. includes controllable factors such as the tools

Show more Read less
Institution
CAPM - Certified Associate In Project Management
Course
CAPM - Certified Associate in Project Management











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CAPM - Certified Associate in Project Management
Course
CAPM - Certified Associate in Project Management

Document information

Uploaded on
May 29, 2024
Number of pages
78
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
AcademiaExpert Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
1695
Member since
4 year
Number of followers
762
Documents
3965
Last sold
4 hours ago
EXAMS, STUDY GUIDES, ESSAYS, NOTES & GOOD GRADES

Hello, my name is Archie. I am an experienced tutor and I am here to provide you with all your study solutions ranging from exams, study guides, essays, notes and just to make school a little bit easier for you. Engage me if you have any questions about your course and I will swiftly and gladly assist. Good luck with studying and all the best going forward.

3.8

429 reviews

5
199
4
81
3
74
2
25
1
50

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions