Project management is generally appropriate:
a. for most any situation that requires hard work
b. when the work effort is complex, unique, and uncertain
c. when the work effort is highly standardized
d. when a high-quality product is desired
Your answer is correct.
The correct answer is:
when the work effort is complex, unique, and uncertain
Question 2
Correct
Mark 1.00 out of 1.00
Some notable features of a system are that:
a. it is an assembly of parts (elements)
b. the assembly of parts is affected by being in the system
c. the assembly of parts is of particular interest
d. the assembly of parts does something or has a goal
e. all of the above
Your answer is correct.
The correct answer is:
all of the above
https://mymodules.dtls.unisa.ac.za/mod/quiz/review.php?attempt=17162392&cmid=853427 1/5
, 09/04/2024, 09:45 Assessment 1: Attempt review
Question 3
Correct
Mark 1.00 out of 1.00
The contract statement of work (CSOW) defines
a. the expected performance of the project in terms of scope, requirements,
results, schedules, costs, price, payment schedules
b. ways to handle changes or variations
c. each party’s responsibilities and liabilities
d. any or all of these
Your answer is correct.
The correct answer is:
any or all of these
Question 4
Correct
Mark 1.00 out of 1.00
Which one of the following relate to the major features of the total quality
management model?
a. Teams, systems, tools, communication, culture, commitment, process
customer and supplier.
b. Facilitate communication and sharing of best-practice information.
c. Understanding, managing performance, guiding, planning, policies and
procedures
d. Help improve employee motivation.
e. Develop new knowledge and skill in an organisation.
Your answer is correct.
The correct answer is:
Teams, systems, tools, communication, culture, commitment, process customer
and supplier.
https://mymodules.dtls.unisa.ac.za/mod/quiz/review.php?attempt=17162392&cmid=853427 2/5
UNISA 2024 PRO4801-24-Y Welcome Message Assessment 1
QUIZ
Started on Monday, 8 April 2024, 5:15 PM
State Finished
Completed on Tuesday, 9 April 2024, 9:42 AM
Time taken 16 hours 27 mins
Marks 10.00/10.00
Grade 100.00 out of 100.00
Question 1
Correct
Mark 1.00 out of 1.00
Project management is generally appropriate:
a. for most any situation that requires hard work
b. when the work effort is complex, unique, and uncertain
c. when the work effort is highly standardized
d. when a high-quality product is desired
Your answer is correct.
The correct answer is:
when the work effort is complex, unique, and uncertain
Question 2
Correct
Mark 1.00 out of 1.00
Some notable features of a system are that:
a. it is an assembly of parts (elements)
b. the assembly of parts is affected by being in the system
c. the assembly of parts is of particular interest
d. the assembly of parts does something or has a goal
e. all of the above
Your answer is correct.
The correct answer is:
all of the above
https://mymodules.dtls.unisa.ac.za/mod/quiz/review.php?attempt=17162392&cmid=853427 1/5
, 09/04/2024, 09:45 Assessment 1: Attempt review
Question 3
Correct
Mark 1.00 out of 1.00
The contract statement of work (CSOW) defines
a. the expected performance of the project in terms of scope, requirements,
results, schedules, costs, price, payment schedules
b. ways to handle changes or variations
c. each party’s responsibilities and liabilities
d. any or all of these
Your answer is correct.
The correct answer is:
any or all of these
Question 4
Correct
Mark 1.00 out of 1.00
Which one of the following relate to the major features of the total quality
management model?
a. Teams, systems, tools, communication, culture, commitment, process
customer and supplier.
b. Facilitate communication and sharing of best-practice information.
c. Understanding, managing performance, guiding, planning, policies and
procedures
d. Help improve employee motivation.
e. Develop new knowledge and skill in an organisation.
Your answer is correct.
The correct answer is:
Teams, systems, tools, communication, culture, commitment, process customer
and supplier.