Master Electrician (First Set 1-85) with Complete Solutions!
A 150 kVA service transformer has a 480Y/277 volt 3-phase primary and a 208Y/120 volt, 3-phase secondary. What is the approximate full-load ampere rating of the primary of the transformer? - ANSWER-180 amperes Where a conductor is marked RHW-2 on the insulation what does the "-2" represent? - ANSWER-The conductor has a maximum operating temperate of 90 degrees C. For a grounded electrical system supplied by a feeder or branch circuit, the equipment grounding conductor shall be sized in accordance with _____. - ANSWER-the overcurrent protective device For lighting systems operating at 30-volts or less, the output circuits of the power supply are to be rated for NOT more than _____. - ANSWER-25 amperes Using the standard method of calculation, what is the demand, in kW, on the ungrounded (line) service-entrance conductors of an apartment complex that has thirty-five (35) electric ranges rated at 11.5 kW each? - ANSWER-50 kW Where a service riser is installed in a wet location and contains THWN insulated conductors, the wiring method used _____. - ANSWER-is permitted to be electrical metallic tubing (EMT) What is the MAXIMUM distance between supports for straight horizontal runs of trade size 1½ in. threaded rigid metal conduit (RMC)? - ANSWER-14 feet Overcurrent protection of transformers, of 600 volts or less, is required to be sized _____. - ANSWER-in accordance with Table 450.3(B) A thermal barrier shall be required if the space between the resistors and reactors, of 600 volts or less, and combustible material is LESS than _____. - ANSWER-12 inches In movie theaters, all switches for controlling the emergency lighting systems shall be located _____. - ANSWER-in the lobby Where a 90 ampere, 240-volt, single-phase load is located 225 feet from a panelboard and is supplied with size 3 AWG copper conductors, determine the approximate voltage drop on the conductors. (K = 12.9) - ANSWER-10 volts Wiring methods associated with solar photovoltaic (PV) systems shall not be installed within _____ of the roof decking or sheathing except where directly below the roof surface covered by PV modules and associated equipment. - ANSWER-10 inches All metallic switchgear rated for over 600 volts shall be provided with a grounding busbar for the purpose of connecting the _____. - ANSWER-metallic shield of cables Conductors tapped from a feeder and supplying the primary of a transformer need not have overcurrent protection, where the length of the tap conductors are not over 25 feet and have an ampacity of at LEAST _____ of the rating of the overcurrent device protecting the feeder conductors. - ANSWER-one-third Electrical equipment such as switchboards, panelboards, industrial control panels, and
Written for
- Institution
- Master Electrician
- Course
- Master Electrician
Document information
- Uploaded on
- February 13, 2024
- Number of pages
- 8
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
master electrician first set 1 85 with complete
-
master electrician first set 1 85stuvia
Also available in package deal