BCF 130 - MOD 12-14 EXAM. QUESTIONS WITH ANSWERS. 2022. 1) The life cycle cost estimate need to be compared to the program affordability analysis to ensure it falls within the affordability caps. True False 2) You estimated that a Naval communications research contract will cost $350.0 K (CY16). You plan to award this 12-month contract in 2019. Using inflation indices from the table, what should your budget request be in TY dollars? $372.0 K None of these are correct. $329.3 K $368.4 K 3) Documentation of the steps taken to develop the estimate is necessary so that a cost analyst unfamiliar with the program can recreate it and produce the same result. True False 4) After aggregating all of the individual distributions during a symmetric approximation into a total cost distribution, we have plotted the Cumulative Distribution Function (CDF) (see chart). How much funding would be required for an 80% chance of an overrun (20% chance of an underrun)? 220 $M 160 $M 140 $M 2 1 2 1 171 $M 5) When preparing for a Defense Acquisition Board (DAB) review, there is a timeline established by the OSD Cost Assessment and Program Evaluation (CAPE). How many days prior to OIPT is required for the OSD CA, PMO and SCA to meet and compare and discuss CCP and ICE. 45 days 28 days None of these are correct 10 days 6) Purchases of end items, weapons and equipment greater than $250,000 intended for operational use or inventory are funded from which appropriation? Procurement MILCON RDT&E O&M 7) In this course we base Symmetric Approximation around a five-step process. Step 1 of the process focuses on selecting which of the following (select two): High dollar cost elements Element that are sensitive to changes made Low dollar cost elements Element which have a small range in potential value. 8) If we were purchasing a helicopter for operational use, funding half of the cost of the helicopter in one year`s appropriation and funding the second half of the cost in the next year`s appropriation would be an example of: 1

Content preview

1) The life cycle cost estimate need to be compared to the program affordability analysis to
ensure it falls within the affordability caps.
10164704 2

True

False

2) You estimated that a Naval communications research contract will cost $350.0 K (CY16).
You plan to award this 12-month contract in 2019. Using inflation indices from the table, what
should your budget request be in TY dollars?
10166026 1




$372.0 K

None of these are correct.

$329.3 K

$368.4 K

3) Documentation of the steps taken to develop the estimate is necessary so that a cost analyst
unfamiliar with the program can recreate it and produce the same result.
10164682 2

True

False

4) After aggregating all of the individual distributions during a symmetric approximation into a
total cost distribution, we have plotted the Cumulative Distribution Function (CDF) (see chart).
How much funding would be required for an 80% chance of an overrun (20% chance of an
underrun)?
10166018 1




220 $M

160 $M

140 $M

, 171 $M

5) When preparing for a Defense Acquisition Board (DAB) review, there is a timeline
established by the OSD Cost Assessment and Program Evaluation (CAPE). How many days
prior to OIPT is required for the OSD CA, PMO and SCA to meet and compare and discuss
CCP and ICE.
10164688 1

45 days

28 days

None of these are correct

10 days

6) Purchases of end items, weapons and equipment greater than $250,000 intended for
operational use or inventory are funded from which appropriation?
10164700 1

Procurement

MILCON

RDT&E

O&M

7) In this course we base Symmetric Approximation around a five-step process. Step 1 of the
process focuses on selecting which of the following (select two):
10164676 6

High dollar cost elements

Element that are sensitive to changes made

Low dollar cost elements

Element which have a small range in potential value.

8) If we were purchasing a helicopter for operational use, funding half of the cost of the
helicopter in one year`s appropriation and funding the second half of the cost in the next year`s
appropriation would be an example of:
10164694 1

Document information

Uploaded on
August 18, 2022
Number of pages
10
Written in
2022/2023
Type
Exam (elaborations)
Contains
Questions & answers
$12.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
registered_nurse
4.0
(132)
Sold
656
Followers
586
Items
1536
Last sold
4 months ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions