Project Fundamentals & Integration
1.
A project manager is beginning a new project and wants to formally
authorize the project and provide authority to use organizational
resources. Which document should be created?
A. Project management plan
B. Scope baseline
C. Project charter
D. Benefits management plan
Answer: C. Project charter
The project charter formally authorizes the project and gives the
project manager authority to apply organizational resources.
2.
Which characteristic best distinguishes a project from operational
work?
,A. Projects are performed by teams.
B. Projects require budgets.
C. Projects are managed by executives.
D. Projects are temporary and create a unique result.
Answer: D. Projects are temporary and create a unique result.
Projects have a defined beginning and end and produce a unique
product, service, or result.
3.
A project manager discovers that a stakeholder has conflicting
expectations about the project's deliverables. What should the
project manager do first?
A. Escalate the conflict to the sponsor.
B. Update the scope baseline.
C. Meet with the stakeholder to understand and clarify the
expectations.
D. Ask the team to determine which expectation is correct.
Answer: C. Meet with the stakeholder to understand and clarify the
expectations.
The project manager should first understand the source of the
conflict before deciding on corrective action or escalation.
4.
Which activity is most appropriate during project initiation?
A. Develop the work breakdown structure.
B. Estimate activity durations.
C. Identify key stakeholders.
D. Create the detailed project schedule.
,Answer: C. Identify key stakeholders.
Stakeholder identification begins early because stakeholders can
significantly influence project requirements and outcomes.
5.
A project manager receives a request to add a major feature that
was not included in the approved scope. What should the project
manager do?
A. Add the feature immediately.
B. Reject the request automatically.
C. Ask the team to work overtime.
D. Evaluate the request through the appropriate change control
process.
Answer: D. Evaluate the request through the appropriate change
control process.
Changes to approved baselines should be evaluated for impact and
processed through the project's change management approach.
6.
Which document describes how the project will be executed,
monitored, controlled, and closed?
A. Project charter
B. Project management plan
C. Business case
D. Stakeholder register
Answer: B. Project management plan
The project management plan integrates the subsidiary plans and
baselines used to manage the project.
, 7.
A project manager is working with a team to identify all work
required to produce the project's deliverables. Which tool is most
useful?
A. Risk register
B. Stakeholder register
C. Work breakdown structure (WBS)
D. Communications matrix
Answer: C. Work breakdown structure (WBS)
The WBS decomposes project scope into manageable components of
work.
8.
What is the primary purpose of a WBS?
A. Assign individual employees to activities
B. Calculate earned value
C. Decompose the total project scope into manageable components
D. Identify project risks
Answer: C. Decompose the total project scope into manageable
components
The WBS organizes and defines the total scope of the project.
9.
A project manager wants to ensure that project activities remain
aligned with organizational strategy. What should the project
manager review?
(PMP) Certification Exam (AGACNP-C)
Practice Exam 2026 |Most Tested
Questions Collection & Verified
Detailed Answers | Tutor Verified
Success Exam) Graded A+
Project Fundamentals & Integration
1.
A project manager is beginning a new project and wants to formally
authorize the project and provide authority to use organizational
resources. Which document should be created?
A. Project management plan
B. Scope baseline
C. Project charter
D. Benefits management plan
Answer: C. Project charter
The project charter formally authorizes the project and gives the
project manager authority to apply organizational resources.
2.
Which characteristic best distinguishes a project from operational
work?
,A. Projects are performed by teams.
B. Projects require budgets.
C. Projects are managed by executives.
D. Projects are temporary and create a unique result.
Answer: D. Projects are temporary and create a unique result.
Projects have a defined beginning and end and produce a unique
product, service, or result.
3.
A project manager discovers that a stakeholder has conflicting
expectations about the project's deliverables. What should the
project manager do first?
A. Escalate the conflict to the sponsor.
B. Update the scope baseline.
C. Meet with the stakeholder to understand and clarify the
expectations.
D. Ask the team to determine which expectation is correct.
Answer: C. Meet with the stakeholder to understand and clarify the
expectations.
The project manager should first understand the source of the
conflict before deciding on corrective action or escalation.
4.
Which activity is most appropriate during project initiation?
A. Develop the work breakdown structure.
B. Estimate activity durations.
C. Identify key stakeholders.
D. Create the detailed project schedule.
,Answer: C. Identify key stakeholders.
Stakeholder identification begins early because stakeholders can
significantly influence project requirements and outcomes.
5.
A project manager receives a request to add a major feature that
was not included in the approved scope. What should the project
manager do?
A. Add the feature immediately.
B. Reject the request automatically.
C. Ask the team to work overtime.
D. Evaluate the request through the appropriate change control
process.
Answer: D. Evaluate the request through the appropriate change
control process.
Changes to approved baselines should be evaluated for impact and
processed through the project's change management approach.
6.
Which document describes how the project will be executed,
monitored, controlled, and closed?
A. Project charter
B. Project management plan
C. Business case
D. Stakeholder register
Answer: B. Project management plan
The project management plan integrates the subsidiary plans and
baselines used to manage the project.
, 7.
A project manager is working with a team to identify all work
required to produce the project's deliverables. Which tool is most
useful?
A. Risk register
B. Stakeholder register
C. Work breakdown structure (WBS)
D. Communications matrix
Answer: C. Work breakdown structure (WBS)
The WBS decomposes project scope into manageable components of
work.
8.
What is the primary purpose of a WBS?
A. Assign individual employees to activities
B. Calculate earned value
C. Decompose the total project scope into manageable components
D. Identify project risks
Answer: C. Decompose the total project scope into manageable
components
The WBS organizes and defines the total scope of the project.
9.
A project manager wants to ensure that project activities remain
aligned with organizational strategy. What should the project
manager review?