Question 1
A project team has been struggling with low morale and missed commitments for
the past two sprints. The project manager notices that team members are avoiding
each other in daily stand-ups and communication has become curt. What should
the project manager do FIRST?
A. Escalate the performance issues to the functional managers of each team
member
B. Schedule individual private meetings with each team member to understand
underlying concerns
C. Replace underperforming team members with new resources
D. Implement a stricter reporting structure with daily status reports
Correct Answer: B
,Rationale: The PMP ECO 2026 People Domain emphasizes building trust and
leading through coaching, not just instruction. Before taking any corrective action,
the project manager must first understand the root cause of the conflict and morale
issues. Individual private meetings allow team members to speak openly without
fear of judgment, enabling the project manager to identify whether the issues stem
from interpersonal conflict, workload problems, unclear expectations, or external
factors. Escalation (A) bypasses the project manager's responsibility to lead the
team. Replacement (C) is premature without understanding the root cause. Stricter
reporting (D) would likely worsen morale by eroding trust further.
Question 2
A project manager is leading a globally distributed team across four time zones.
Stakeholders in the headquarters location have complained that they feel "out of
the loop" on project decisions. What should the project manager do?
A. Schedule weekly face-to-face meetings at headquarters for all key stakeholders
B. Create a communication management plan that addresses the information needs
of all stakeholder groups
C. Send daily email updates to all stakeholders regardless of their preference
D. Assign a team member in headquarters to act as a liaison
Correct Answer: B
Rationale: The People Domain requires project managers to plan communication
strategically and manage stakeholder expectations. A communication management
plan ensures that the right information reaches the right stakeholders at the right
time through the appropriate channels. Weekly face-to-face meetings (A) may not
be feasible for a distributed team and could be excessive. Daily emails (C) would
create information overload and may not address the specific concerns of
headquarters stakeholders. A liaison (D) is a partial solution that doesn't address
the underlying communication gap.
Question 3
During a project review, a senior stakeholder demands that the project team add a
new feature that was explicitly excluded from the project scope. The stakeholder
,threatens to withdraw funding if the feature is not included. What should the
project manager do NEXT?
A. Immediately add the feature to avoid losing funding
B. Escalate the issue to the project sponsor
C. Schedule a meeting with the stakeholder to review the scope baseline and
discuss the impact of the change
D. Add the feature but reduce scope elsewhere to maintain the budget
Correct Answer: C
Rationale: The correct approach is to engage the stakeholder in a conversation
about the scope baseline and the implications of the proposed change. This
demonstrates leadership and stakeholder engagement skills from the People
Domain while also respecting the Process Domain's scope management practices.
Immediate addition (A) would violate change control processes. Escalation (B)
should occur only after the project manager has attempted direct engagement.
Reducing scope elsewhere (D) without proper analysis could jeopardize other
deliverables.
Question 4
A project manager has been assigned to a troubled project. The previous project
manager left abruptly, and the team is disengaged and lacks clear direction. What
should the new project manager do FIRST?
A. Develop a common vision for the project and facilitate team alignment around
that vision
B. Review all project documentation to understand what went wrong
C. Hold a team meeting to assign new responsibilities
D. Request a new team from the functional manager
Correct Answer: A
Rationale: According to the PMP ECO 2026, Task 1.1 requires project managers
to "Develop a common vision" as a foundational leadership competency. A shared
vision provides direction and purpose, which is critical when a team is disengaged.
While reviewing documentation (B) is important, it should not be the FIRST
action. Assigning responsibilities (C) without establishing vision and trust would
, likely be resisted. Requesting a new team (D) is an extreme measure that avoids
addressing the core leadership challenge.
Question 5
Two senior team members disagree on the technical approach for a critical project
component. Both approaches are technically valid but have different cost and
schedule implications. The disagreement has escalated and is now affecting team
morale. What should the project manager do?
A. Choose the approach that aligns with the project sponsor's preferences
B. Facilitate a structured discussion where both parties present their cases, then
help the team reach consensus
C. Assign each team member to a different workstream to avoid further conflict
D. Escalate the technical decision to a steering committee
Correct Answer: B
Rationale: The People Domain emphasizes conflict management and resolution.
The project manager's role is to facilitate collaboration and help the team reach a
consensus-based decision. This approach respects both team members' expertise
while maintaining team cohesion. Choosing based on sponsor preference (A)
undermines team empowerment. Separation (C) avoids the conflict rather than
resolving it. Escalation (D) should be reserved for decisions that exceed the project
manager's authority or when consensus is genuinely impossible.
Question 6
A project manager notices that one team member consistently delivers high-quality
work but frequently misses deadlines, causing downstream delays. The team
member has not responded to informal reminders. What should the project
manager do?
A. Immediately place the team member on a performance improvement plan
B. Have a private coaching conversation to understand the root cause of the delays
and develop a plan together
C. Assign the team member's work to other team members
D. Document the performance issues and report them to HR
Latest Comprehensive Study Guide Practice
Questions, Detailed Explanations, Verified Answers &
Complete Success Preparation Workbook
Exam Overview (ECO 2026 - Effective July 9, 2026)
Domain Weight Approx. Scored Questions
People 33% ~56 questions
Process 41% ~70 questions
Business Environment 26% ~44 questions
PEOPLE DOMAIN (33%) — Leadership, Team Performance,
Communication, Collaboration, Conflict, Stakeholder Engagement, Coaching
Question 1
A project team has been struggling with low morale and missed commitments for
the past two sprints. The project manager notices that team members are avoiding
each other in daily stand-ups and communication has become curt. What should
the project manager do FIRST?
A. Escalate the performance issues to the functional managers of each team
member
B. Schedule individual private meetings with each team member to understand
underlying concerns
C. Replace underperforming team members with new resources
D. Implement a stricter reporting structure with daily status reports
Correct Answer: B
,Rationale: The PMP ECO 2026 People Domain emphasizes building trust and
leading through coaching, not just instruction. Before taking any corrective action,
the project manager must first understand the root cause of the conflict and morale
issues. Individual private meetings allow team members to speak openly without
fear of judgment, enabling the project manager to identify whether the issues stem
from interpersonal conflict, workload problems, unclear expectations, or external
factors. Escalation (A) bypasses the project manager's responsibility to lead the
team. Replacement (C) is premature without understanding the root cause. Stricter
reporting (D) would likely worsen morale by eroding trust further.
Question 2
A project manager is leading a globally distributed team across four time zones.
Stakeholders in the headquarters location have complained that they feel "out of
the loop" on project decisions. What should the project manager do?
A. Schedule weekly face-to-face meetings at headquarters for all key stakeholders
B. Create a communication management plan that addresses the information needs
of all stakeholder groups
C. Send daily email updates to all stakeholders regardless of their preference
D. Assign a team member in headquarters to act as a liaison
Correct Answer: B
Rationale: The People Domain requires project managers to plan communication
strategically and manage stakeholder expectations. A communication management
plan ensures that the right information reaches the right stakeholders at the right
time through the appropriate channels. Weekly face-to-face meetings (A) may not
be feasible for a distributed team and could be excessive. Daily emails (C) would
create information overload and may not address the specific concerns of
headquarters stakeholders. A liaison (D) is a partial solution that doesn't address
the underlying communication gap.
Question 3
During a project review, a senior stakeholder demands that the project team add a
new feature that was explicitly excluded from the project scope. The stakeholder
,threatens to withdraw funding if the feature is not included. What should the
project manager do NEXT?
A. Immediately add the feature to avoid losing funding
B. Escalate the issue to the project sponsor
C. Schedule a meeting with the stakeholder to review the scope baseline and
discuss the impact of the change
D. Add the feature but reduce scope elsewhere to maintain the budget
Correct Answer: C
Rationale: The correct approach is to engage the stakeholder in a conversation
about the scope baseline and the implications of the proposed change. This
demonstrates leadership and stakeholder engagement skills from the People
Domain while also respecting the Process Domain's scope management practices.
Immediate addition (A) would violate change control processes. Escalation (B)
should occur only after the project manager has attempted direct engagement.
Reducing scope elsewhere (D) without proper analysis could jeopardize other
deliverables.
Question 4
A project manager has been assigned to a troubled project. The previous project
manager left abruptly, and the team is disengaged and lacks clear direction. What
should the new project manager do FIRST?
A. Develop a common vision for the project and facilitate team alignment around
that vision
B. Review all project documentation to understand what went wrong
C. Hold a team meeting to assign new responsibilities
D. Request a new team from the functional manager
Correct Answer: A
Rationale: According to the PMP ECO 2026, Task 1.1 requires project managers
to "Develop a common vision" as a foundational leadership competency. A shared
vision provides direction and purpose, which is critical when a team is disengaged.
While reviewing documentation (B) is important, it should not be the FIRST
action. Assigning responsibilities (C) without establishing vision and trust would
, likely be resisted. Requesting a new team (D) is an extreme measure that avoids
addressing the core leadership challenge.
Question 5
Two senior team members disagree on the technical approach for a critical project
component. Both approaches are technically valid but have different cost and
schedule implications. The disagreement has escalated and is now affecting team
morale. What should the project manager do?
A. Choose the approach that aligns with the project sponsor's preferences
B. Facilitate a structured discussion where both parties present their cases, then
help the team reach consensus
C. Assign each team member to a different workstream to avoid further conflict
D. Escalate the technical decision to a steering committee
Correct Answer: B
Rationale: The People Domain emphasizes conflict management and resolution.
The project manager's role is to facilitate collaboration and help the team reach a
consensus-based decision. This approach respects both team members' expertise
while maintaining team cohesion. Choosing based on sponsor preference (A)
undermines team empowerment. Separation (C) avoids the conflict rather than
resolving it. Escalation (D) should be reserved for decisions that exceed the project
manager's authority or when consensus is genuinely impossible.
Question 6
A project manager notices that one team member consistently delivers high-quality
work but frequently misses deadlines, causing downstream delays. The team
member has not responded to informal reminders. What should the project
manager do?
A. Immediately place the team member on a performance improvement plan
B. Have a private coaching conversation to understand the root cause of the delays
and develop a plan together
C. Assign the team member's work to other team members
D. Document the performance issues and report them to HR