✔✔ECB and TRM - ✔✔Erosion Control Blanket and Turf Reinforcement Mats
- RECB/ECB = usually put on hillsides
- TRM = usually put on channels
Inspect:
- Has seed been planted before laying the blanket?
- Is the material anchored in a trench?
- Do sufficient staples exist (2 in. apart?)
- Are the edges secure (w staples)?
- Can you pull up the TRM 6-12'? = Not good
✔✔Hard Armoring - ✔✔Using rip rap/ rock on hillsides
-Are animals borrowing in it?
- Is sediment accumulating on rocks?
- Is the rock being undercut or collapsing?
✔✔Cellular confinements - ✔✔Rigid plastic structure where soil can be placed into for
vegetative establishment.
✔✔Inspecting Hazardous and Waste Materials - ✔✔- Are materials stored
appropriately/ preferrably inside.
- Are the materials labeled?
- Are the materials disposed of properly? Is there a portable containment? (Example:
concrete washouts)
- Is there proper protection underneath materials and are they covered?
✔✔Inspecting Portable Toilets - ✔✔- Is it away from an inlet and off of paved roads?
- Are they anchored well and have a secondary containment underneath?
, ✔✔Gabions - ✔✔Steel mesh cages filled with small rocks, absorb wave energy.
✔✔ LDP - ✔✔Land Developing Projects - altering landscape for projects such as
agriculture or housing ect.
✔✔NPDES - ✔✔National Pollutant Discharge Elimination System
- section of the CWA (Clean Water Act) to permit stormwater discharges associated w
industrial activities PER permit
✔✔CWA Penalty Types - ✔✔Adminstrative
Class I. Neglegent
Class II. Knowlingly = greater fines
✔✔What documents are required on site? - ✔✔- SWPPP
- CGP
- Site Map
- Drawings and Key
- All inspection reports
- Any amendments to SWPPP
✔✔Who is the "operator"? Also the LRP. - ✔✔Usually the OWNER of the site, not the
contractor, unless authorized by the owner to general contractor to have day-to-day
operational control!
✔✔When do you need permit coverage? - ✔✔Required from start to end of project.
"End" being the final vegetative/non-vegetative (concrete) stabilization occuring.
For any project one acre or greater.
✔✔Large Land Development - ✔✔-strips off all existing vegetation a.k.a site carving
-usually on hillsides and steep slopes
-installation of untilities that tear up large areas of land
✔✔Vertical Projects - ✔✔- Homebuilding, smaller residence construction projects
-usually multiple subcontractors
-requires lots of housekeeping = mass choas
✔✔Bix Box Projects - ✔✔-commercial buildings
-mass grading and mass choas
-highly visible w/ fairly large footprint
✔✔Linear Projects - ✔✔-roadways, utilities, and stream corridors
-long narrow sites and mass choas
ANSWERS SURE A+
✔✔ECB and TRM - ✔✔Erosion Control Blanket and Turf Reinforcement Mats
- RECB/ECB = usually put on hillsides
- TRM = usually put on channels
Inspect:
- Has seed been planted before laying the blanket?
- Is the material anchored in a trench?
- Do sufficient staples exist (2 in. apart?)
- Are the edges secure (w staples)?
- Can you pull up the TRM 6-12'? = Not good
✔✔Hard Armoring - ✔✔Using rip rap/ rock on hillsides
-Are animals borrowing in it?
- Is sediment accumulating on rocks?
- Is the rock being undercut or collapsing?
✔✔Cellular confinements - ✔✔Rigid plastic structure where soil can be placed into for
vegetative establishment.
✔✔Inspecting Hazardous and Waste Materials - ✔✔- Are materials stored
appropriately/ preferrably inside.
- Are the materials labeled?
- Are the materials disposed of properly? Is there a portable containment? (Example:
concrete washouts)
- Is there proper protection underneath materials and are they covered?
✔✔Inspecting Portable Toilets - ✔✔- Is it away from an inlet and off of paved roads?
- Are they anchored well and have a secondary containment underneath?
, ✔✔Gabions - ✔✔Steel mesh cages filled with small rocks, absorb wave energy.
✔✔ LDP - ✔✔Land Developing Projects - altering landscape for projects such as
agriculture or housing ect.
✔✔NPDES - ✔✔National Pollutant Discharge Elimination System
- section of the CWA (Clean Water Act) to permit stormwater discharges associated w
industrial activities PER permit
✔✔CWA Penalty Types - ✔✔Adminstrative
Class I. Neglegent
Class II. Knowlingly = greater fines
✔✔What documents are required on site? - ✔✔- SWPPP
- CGP
- Site Map
- Drawings and Key
- All inspection reports
- Any amendments to SWPPP
✔✔Who is the "operator"? Also the LRP. - ✔✔Usually the OWNER of the site, not the
contractor, unless authorized by the owner to general contractor to have day-to-day
operational control!
✔✔When do you need permit coverage? - ✔✔Required from start to end of project.
"End" being the final vegetative/non-vegetative (concrete) stabilization occuring.
For any project one acre or greater.
✔✔Large Land Development - ✔✔-strips off all existing vegetation a.k.a site carving
-usually on hillsides and steep slopes
-installation of untilities that tear up large areas of land
✔✔Vertical Projects - ✔✔- Homebuilding, smaller residence construction projects
-usually multiple subcontractors
-requires lots of housekeeping = mass choas
✔✔Bix Box Projects - ✔✔-commercial buildings
-mass grading and mass choas
-highly visible w/ fairly large footprint
✔✔Linear Projects - ✔✔-roadways, utilities, and stream corridors
-long narrow sites and mass choas