APM PMQ Project Management Qualification
Comprehensive Review Examination
150 Questions | Detailed Rationales | Bold Formatting
Q1: Which of the following best describes the primary purpose of a business case in project management?
A. To define the technical specifications and architecture of the project deliverables
B. To provide a justified reason for undertaking the project based on expected benefits, costs, and risks
[CORRECT]
C. To establish the project schedule and resource allocation plan
D. To document the stakeholder communication strategy and engagement approach
Correct Answer: B.
Rationale: Correct because a business case establishes the justification for a project by outlining the expected benefits,
costs, risks, and alignment with strategic objectives. This matches the APM definition which requires a business case to
demonstrate value for money and organizational fit before investment is approved.
Q2: A project manager identifies a senior director who has significant influence over project funding but shows
little interest in the project outcomes. Using a power-interest grid, which engagement strategy is most appropriate?
A. Manage closely with regular detailed reports and meetings
B. Keep satisfied with periodic high-level updates on progress and key decisions [CORRECT]
C. Monitor with minimal effort and provide information only when requested
D. Involve actively in day-to-day decision-making and seek their input on all issues
Correct Answer: B.
Rationale: Correct because a stakeholder with high power but low interest falls into the 'keep satisfied' quadrant of the
power-interest grid. This matches the APM guidance that such stakeholders should receive adequate attention to
prevent them becoming blockers, but do not require intensive engagement needed by those who are also highly
interested.
Q3: In a project network diagram, Activity A (5 days) and Activity B (3 days) can start together. Both feed into
Activity C (4 days). If Activity A starts on Day 1, what is the earliest finish date for Activity C?
A. Day 9
B. Day 12
C. Day 10 [CORRECT]
D. Day 13
Correct Answer: C.
Rationale: Correct because the earliest finish for Activity C is determined by the latest predecessor. Activity A finishes
on Day 5, so Activity C starts on Day 6 and finishes on Day 9 (Day 6 + 4 - 1 = Day 9). However, with both A and B
feeding into C, the earliest C can start is after A finishes on Day 5 (since A is the longer predecessor), so C runs Days
6-9. Priority is identifying the longest path through the network to calculate correct earliest finish dates.
Q4: Which risk response strategy involves transferring the financial impact of a threat to a third party?
A. Risk avoidance
B. Risk mitigation
C. Risk transfer [CORRECT]
D. Risk acceptance
Correct Answer: C.
Page 1
,APM PMQ Comprehensive Review Examination 150 Questions
Rationale: Correct because risk transfer involves shifting the financial consequence of a threat to a third party,
typically through insurance, warranties, or contractual arrangements. This matches the APM Body of Knowledge
definition of transfer as one of the four primary threat response strategies.
Q5: A project has a Budget at Completion (BAC) of 200,000. The Planned Value (PV) is 80,000, the Earned Value
(EV) is 72,000, and the Actual Cost (AC) is 85,000. What is the Cost Performance Index (CPI)?
A. 0.90
B. 1.18
C. 0.85 [CORRECT]
D. 0.94
Correct Answer: C.
Rationale: Correct because the Cost Performance Index is calculated as EV divided by AC: 72,000 divided by 85,000
equals 0.847, which rounds to 0.85. This matches the standard EVM formula CPI = EV / AC, where a value below 1.0
indicates the project is over budget.
Q6: What is the primary role of a Project Board in project governance?
A. To manage the day-to-day activities of the project team
B. To provide strategic direction, make key decisions, and ensure organizational alignment
[CORRECT]
C. To prepare detailed project plans and track progress against milestones
D. To negotiate contracts with suppliers and manage procurement activities
Correct Answer: B.
Rationale: Correct because the Project Board exists to provide strategic oversight, authorize major decisions, and
ensure the project remains aligned with organizational objectives. This matches the APM definition of governance as
the framework of authority and accountability that defines and controls the outputs, outcomes, and benefits of
projects.
Q7: A project manager needs to communicate a significant schedule delay to both the project sponsor and the
wider project team. Which approach best demonstrates effective communication management?
A. Send the same detailed email to all stakeholders simultaneously to ensure consistency
B. Tailor the message content and level of detail to each audience group based on their needs and
interests [CORRECT]
C. Wait until the next scheduled steering group meeting to raise the issue formally
D. Communicate only with the project team and let the sponsor discover the delay through regular reports
Correct Answer: B.
Rationale: Correct because effective communication management requires tailoring messages to the specific needs,
concerns, and decision-making responsibilities of each stakeholder group. This matches the APM principle that
communication should be targeted, timely, and in an appropriate format for the intended audience.
Q8: In the Scrum framework, what is the maximum recommended duration of a sprint?
A. One week
B. Two weeks
C. Four weeks [CORRECT]
D. Six weeks
Correct Answer: C.
Rationale: Correct because the Scrum Guide states that sprints should be timeboxed to one month or less, with a
preference for shorter durations. This matches the APM Body of Knowledge recognition that Scrum sprints typically
range from one to four weeks, with many organizations adopting two-week cycles.
Page 2
,APM PMQ Comprehensive Review Examination 150 Questions
Q9: A project has delivered its outputs on time and within budget, but the expected operational efficiency benefits
have not materialized six months after handover. Which aspect of benefits management was most likely neglected?
A. Benefits identification during the business case development
B. Benefits realization planning and transition ownership [CORRECT]
C. Benefits mapping to project deliverables during planning
D. Benefits profiling and categorization at project initiation
Correct Answer: B.
Rationale: Correct because benefits realization planning ensures that arrangements are in place for benefits to be
achieved after project outputs have been delivered, including assigning ownership of benefits to operational managers.
Priority is the transition from project outputs to business-as-usual operations, which is where the gap between delivery
and benefit achievement most commonly occurs.
Q10: Under a fixed-price contract, which party bears the greatest financial risk if actual costs exceed the agreed
price?
A. The client
B. The supplier [CORRECT]
C. Both parties share the risk equally
D. The project manager
Correct Answer: B.
Rationale: Correct because in a fixed-price contract the supplier agrees to deliver the specified scope for a set price,
meaning the supplier absorbs any cost overruns. This matches the APM guidance that fixed-price contracts transfer
cost risk to the supplier, making them most appropriate when requirements are well-defined and stable.
Q11: During a quality audit of a construction project, the auditor discovers that welding inspections are being
recorded but the inspection criteria are not documented. What is the most appropriate corrective action?
A. Stop all welding work immediately until the criteria are agreed
B. Document the quality acceptance criteria and ensure all inspectors are briefed on the standards
[CORRECT]
C. Accept the current inspections as valid since they were performed by qualified personnel
D. Report the finding to the Project Board and await their decision before proceeding
Correct Answer: B.
Rationale: Correct because quality management requires defined acceptance criteria to ensure consistency and
objectivity in inspections. This matches the APM quality planning principle that quality standards and acceptance
criteria must be established before quality control activities can be effective.
Q12: Which project life cycle model is characterized by sequential phases with formal gate reviews between each
phase?
A. Adaptive life cycle
B. Incremental life cycle
C. Predictive (waterfall) life cycle [CORRECT]
D. Iterative life cycle
Correct Answer: C.
Rationale: Correct because the predictive or waterfall life cycle follows a sequential flow through defined phases with
formal approval points or gates between each stage. This matches the APM description of the linear life cycle where
each phase must be completed before the next begins.
Q13: A project requires an initial investment of 150,000 and is expected to generate annual net cash inflows of
40,000 for five years. Which financial appraisal technique is most suitable for determining viability?
Page 3
, APM PMQ Comprehensive Review Examination 150 Questions
A. Payback period
B. Net Present Value (NPV) [CORRECT]
C. Cost-benefit ratio
D. Return on investment (ROI)
Correct Answer: B.
Rationale: Correct because Net Present Value accounts for the time value of money by discounting future cash flows,
which is essential when evaluating a project with cash inflows spread over multiple years. This matches the APM
guidance that NPV is the preferred investment appraisal technique when comparing projects with different cash flow
profiles and time horizons.
Q14: A project team has been working together for three months and is now experiencing open disagreements
about technical approaches. Team members express frustration but also begin to share creative ideas. Which stage
of Tuckman's model does this represent?
A. Forming
B. Storming [CORRECT]
C. Norming
D. Performing
Correct Answer: B.
Rationale: Correct because the storming stage is characterized by conflict, competition, and disagreement as team
members challenge each other's ideas and jockey for position. This matches Tuckman's model where storming follows
the initial forming stage and precedes the establishment of norms and high performance.
Q15: A client requests a scope change that will add 15% to the project cost but deliver significant additional
business value. The project manager has not yet assessed the impact on schedule or resources. What should happen
next?
A. Reject the change immediately as it exceeds the agreed budget tolerance
B. Accept the change since it delivers additional business value and inform the sponsor
C. Log the change request, conduct a full impact assessment, and present findings to the change
authority [CORRECT]
D. Implement the change and adjust the budget through contingency reserves
Correct Answer: C.
Rationale: Correct because change control requires that all change requests are formally logged, their impact on scope,
schedule, cost, and risk is assessed, and then a decision is made by the authorized change authority. Priority is
following the established change control process rather than making ad hoc decisions based on incomplete information.
Q16: What is the primary purpose of a Work Breakdown Structure (WBS)?
A. To assign resources to project tasks and create a responsibility matrix
B. To decompose the total project scope into manageable, hierarchical work packages [CORRECT]
C. To identify the critical path and determine the project duration
D. To establish the project budget and track actual expenditure against planned costs
Correct Answer: B.
Rationale: Correct because a WBS is a hierarchical decomposition of the total scope of work to be carried out by the
project team to accomplish project objectives and create the required deliverables. This matches the APM definition
that the WBS organizes and defines the total scope of the project.
Q17: Scenario: A key supplier has informed you that material costs have increased by 20% since the contract was
signed. The supplier is requesting a contract amendment. The project budget has no contingency remaining. Which
negotiation approach is most likely to achieve a mutually acceptable outcome?
A. Insist on the original contract terms since a legally binding agreement is in place
Page 4